Construction Tips, News & Best Practices
Working in construction can often feel like an exercise in educated guesswork.
Even the best project managers can be defeated by circumstances outside of their control, be it weather, no-show deliveries or unavailable subcontractors.
And once the wheels start to come off the proverbial digger, your budget and timescales are at risk.
So, here’s the issue:
Making a profit in construction requires predicting the unpredictable. So how do you do that? The solution lies in construction work-in-progress reporting.
How does it work? Here's what we'll cover:
One of the biggest challenges in construction accounting is that income and their corresponding expenses rarely occur in the same billing period.
That makes it difficult to track your budget because you’re often not looking at the whole story.
Consider this example: Let’s pretend you own a building company called Cornerstone Construction and you’ve billed your client, say, £100,000 in the last month.
But looking at your balance sheet, you realise the costs over the same period are only £50,000 – much less than the projected £90,000.
In short, the project is now massively over-billed. Quids in, you think – turns out this project is going to be more profitable than you thought!
If only life were so simple…
Check out our recent rundown on construction accounting to find out more about construction accounting processes.
The truth is that over-billing is much more of a red flag than it originally looks.
The most likely explanation is that the work hasn’t been completed yet, meaning you could be in for a shockingly high bill later when all those extra costs get spent.
It could also indicate that the work is moving too slowly – meaning you may end up blowing your timescale and budget at the end of the project.
So, what does this have to do with work-in-progress reporting?
In short, your WIP report is your opportunity to work out how on track your construction projects are from month to month, so you can rectify issues and avoid ugly surprises later on.
So all this begs the question: What are construction WIP reports – and how does it help you keep track of your project’s balance sheet?
In essence, the goal is to compare the total expenses so far with the total projected expenses of the project, to work out whether or not you are under or over-billed.
Over or under-billing can be perfectly innocent or a massive red flag – depending on the project you’re working on.
Most building work will start over-billed, for instance, as clients are generally expected to pay a deposit up-front before work begins.
But it’s important to know why you’re producing the figures you are - so you can find and resolve potential issues before they start to send your project off the rails.
For WIP reports to work properly, there’s a certain amount of information it’s important to give.
First, you need to recap the original projected costs of the project, including:
Then, you need to include details of actual spend-to-date – so you can compare the reality against the projection:
This will then allow you to produce figures to assess how on track the project is. These include:
These figures will help you understand if your project is on track and whether profits are at risk. Then you can use that information to proactively spot any issues.
When it comes to your WIP report, there are three main metrics you need to calculate:
The percentage completion is quite simply a proportion of the total project value you’ve already spent. You can calculate it like this:
You can use the percentage completion to then calculate your estimated profits to date:
From there, you can deduce how on track your budget really is:
If the resulting number is above 0, the project is over-billed, if it’s under, then you’re under-billing.
To see the WIP report in action, let’s return for a moment to Cornerstone Construction and consider how these calculations can help us produce a more accurate overview of our project.
Let’s assume the following estimated cost outline was created at the start of the project:
Now, one month in, the actual spent cash flow looks a little more like this:
From this, therefore, we can calculate:
In short, you’ve used about half the budget you expected, and the project is now £45,000 over-billed.
With the project being only 25% complete, you can calculate your profit share thus far as £5,000 – 25% of the total expected profit.
Compare that to where we were at the start, when a simple calculation of £100,000 (Total billed) - £50,000 (Total spent to date) made your profit margins look a lot healthier than they actually are.
So where do you go now? What’s the solution to over/ or under-billing and how do you get your project back on track?
Unfortunately, the solution here is often a lot more difficult to define.
There could be plenty of reasons why a project is over or under-billed, some sensible, others worrying.
The key is to discuss the WIP report with your Project Manager to understand more about the situation on the ground.
From there, you can determine whether you need to change your plan to get the project on track, or whether you can expect next month’s finances to make up the difference.
When building your WIP reporting, there are a few pitfalls you need to watch out for:
For WIP reports to do their job, you need to create them regularly, ideally weekly, fortnightly or monthly – depending on the length of the project.
Otherwise, you run the risk of identifying problems too late in the process to fix them.
If you’re relying on Excel or a similar spreadsheet tool, it can be easy to enter figures wrong or end up with strange results due to broken formulae.
Double-check the figures and, if in doubt, employ the ‘smell test’: If it feels wrong, it probably is.
Assuming over-billing = profit
As we discovered at Cornerstone Construction, over-billing isn’t necessarily a good thing.
If you assume the funds are profit and spend them accordingly – you could be left with significant liability later down the line. Instead, always use the earned revenue method to work out your actual profits.
Using outdated information
When creating your report, use the most up-to-date figures available.
If the data is a few days or even weeks out of date, you’ll lose the opportunity to spot issues that might have arisen in the meantime.
Accurate WIP reporting might seem confusing at first – but it is possible to get it right.
However, if you’re doing much of the reporting on Excel, other spreadsheets, or even paper – there’s a good chance that mistakes will creep in that you’ll struggle to spot.
That’s why it’s so important to ensure you’re using the right technology to support your WIP reporting and construction accounting processes.
A Project Manager can help give you the valuable context behind the numbers in your WIP reports. Crucially, they can help you understand why you are under or over-billing, so you can understand how to get the project back on track.
To create a WIP report, first add the total contract value to date, estimated costs, actual cost to date and total billed revenue. From there, you can calculate the percentage completion, earned revenue and whether the project is over or under-billed.
To make sure your report is on track, always double-check your figures, make sure you’re using the most up-to-date data, report regularly and never assume that over-billing = profit.
Construction-in-progress, or work-in-progress reports, are a type of regular accounting that construction firms use to understand whether ongoing projects are on budget.
Let’s pretend you’re working on a building project for Cornerstone Construction. Construction-in-progress, or work-in-progress reports, help you track your income and expenditure throughout the project to understand whether you’re under or over-billing.
Work-in-progress reporting should include any details of expenditure you’ve spent. That includes material costs, subcontractors and labour.
Sign up today for tips on using free digital tools like Chat GPT and Canva.
May 16, 2024 • 3 min read
May 14, 2024 • 6 min read
February 29, 2024 • 7 min read
July 3, 2023 • 6 min read