Archdesk

WIP & CVR Reporting Software for Irish Contractors

One set of records behind the valuation, the CVR and the WIP.

Percent-complete from actual cost against forecast final, revenue from the live contract value with variations in, over and under-billing by job. Irish commercial teams read the WIP and the CVR from the same records that ran the work, so the monthly position is produced, not assembled.

Get Started
Solution screenshot

Trusted by construction companies of every size, worldwide

Higgins Partnerships logo
QBRE logo
Mitie logo
Daikin logo
VINCI Construction logo
Ballast Nedam logo
Madinet Masr logo
QGMI logo
CDC City Diamond Contracting logo
CSI Energy logo
Polenergia logo
ib vogt logo
TeraWulf logo
Utilligence logo
TaskSpace logo
Echospace logo
EEE Elevator Enterprise logo
Eomac logo
QTS logo
MacLennan logo
Conditioned Environment logo
DVM logo
ADP logo
DMDC logo
Inuti logo
Oakwrights logo
JH logo
K4 logo

The WIP reads from the records, not from a spreadsheet round-robin

Irish contractors already run the month around the valuation and the CVR; the WIP schedule is the same story told to finance. Archdesk produces all of it from one set of live records: committed and actual cost against forecast final, certified valuations, and contract value with approved variations included. Over and under-billing surface by project across the portfolio, retention sits per subcontract beside the numbers it belongs to, and applications for payment run on the same cost codes, so the figure finance books at month end is the figure the commercial team certified.

Engineer in front of a high-rise under construction with tower cranes

Valuations, CVR and the accounts in step

Applications for payment, payment certification and revenue recognition run from the same numbers as the WIP, so finance and commercial never argue over whose figure is right.

Profit fade caught while it is a conversation

Cost-to-complete and margin projections move with the live records, with overrun alerts and trend identification, so profit fade is raised at the commercial review while there is still time to act on it.

Over and under-billing by project

The billing position is visible job by job across the portfolio, with accrue and prepay calculations handled in the report itself, alongside portfolio cashflow.

Percent-complete from cost, not opinion

Progress is read from actual cost against forecast final and certified valuations, the basis the CVR already uses, rather than estimates gathered by email.

Every figure substantiates back to a record

When finance or the auditor queries a line, the answer is a drill-down: certified valuations, commitments, actual cost, retention balances and approved variations, all held in the one system.

Engineer with a tablet inspecting a concrete soffit on site

WIP Reporting

The WIP schedule and the monthly CVR generate from live project data, in the format each stakeholder needs, across the whole portfolio. Nothing is rebuilt in a spreadsheet.

CVR (cost value reconciliation) reports

Over and under-billing by project

Custom templates and executive dashboards

Accrue and prepay calculation

Portfolio cashflow reporting

Stakeholder-specific reporting

WIP Reporting screenshot

Financial Analysis

Cost-to-complete and profit projections run from live data, so the position you report to the accounts is the position the project actually holds.

Cost-to-complete forecasting

Profit and loss projection

Cash flow analysis

Revenue recognition tracking

Financial Analysis screenshot

Progress Claims

Claims generate with the supporting evidence attached, so certification and payment follow the records instead of chasing them.

Automated claim generation

Supporting evidence tracking

Payment certification

Retention management

Progress Claims screenshot

Variance Analysis

Planned against actual on cost, progress and schedule, with alerts the moment a project starts to drift from the plan.

Budget variance tracking

Schedule deviation analysis

Cost overrun alerts

Trend identification

Variance Analysis screenshot

Real-time Progress Tracking

Progress, cost and earned value tracked live across every project, so the WIP reflects the site as it stands today, not as it stood at the last update.

Live progress updates

Cost tracking by trade

Earned value monitoring

Project milestone tracking

Real-time Progress Tracking screenshot

Performance Tracking

Project health visible across the portfolio, so the jobs that need attention get it before the WIP says so.

KPI dashboards

Project health scoring

Resource usage metrics

Productivity analysis

Performance Tracking screenshot

Work in progress reporting, defined

A work in progress (WIP) report shows, for every live contract, how much of the work has been done, how much has been billed, and how far apart those two numbers are. Percent-complete comes from cost incurred against forecast final cost, earned revenue applies that progress to the contract value including approved variations, and the gap between earned and billed is the over- or under-billing position. Read monthly across the portfolio, the WIP is how contractors catch profit fade, under-claimed work and cashflow risk while something can still be done about them.

WIP lineHow it is calculatedWhere it comes from in Archdesk
Percent-completeActual cost to date against forecast final costLive job costing and cost-to-complete forecasting
Earned revenueProgress applied to contract value, approved variations includedContract records with variations on their cost lines
Over / under-billingEarned revenue against billed to dateValuations and certified billing on the same record

Plenty of pages define a WIP schedule. The difference here is that Archdesk produces one: the report builds from the records that ran the work, alongside the monthly CVR (cost value reconciliation), rather than from figures collected by email at month-end.

Frequently Asked Questions: WIP Reporting & CVR

What is construction WIP reporting software?

Software that builds the work-in-progress schedule from operational records instead of spreadsheets. Archdesk produces the WIP from committed and actual cost against forecast final, certified valuations, and contract value with approved variations included, so over and under-billing surface by project across the portfolio.

How is percent-complete calculated?

From actual cost against forecast final cost and certified valuations, not from estimates emailed in by project managers. The WIP reflects the site as it stands today because progress, cost and earned value are tracked live on every project.

What is a CVR (cost value reconciliation) report?

A CVR (cost value reconciliation) compares the cost of the work done against the value earned for it, so the true position of each contract is visible month by month. In Archdesk the monthly CVR generates from live project data alongside the WIP, in the format each stakeholder needs, with nothing rebuilt in a spreadsheet.

How does WIP reporting catch profit fade early?

Cost-to-complete forecasting and profit projections update from live data, with cost overrun alerts and trend identification the moment a project starts to drift. Fade shows up while it is still a conversation, not as a month-nine surprise.

Can WIP figures be substantiated for finance and auditors?

Yes. Every line in the WIP drills down to the records that produced it: valuations, commitments, actual cost and approved variations. Progress claims, payment certification and revenue recognition run from the same numbers, so the figure finance books is the figure the project reported.

What does the CVR add to the WIP schedule?

The CVR (cost value reconciliation) gives the contract-by-contract cost against value picture; the WIP schedule turns the same records into the billing position finance needs. Archdesk produces both from live commitments, valuations and actual cost, at project and portfolio level, so neither is rebuilt in a spreadsheet at month end.

Where does retention sit in the monthly position?

Retention is tracked per subcontract with the rest of the commercial record, so balances and release timing stay visible beside the numbers the WIP and the CVR are produced from, from the first valuation through the defects period.

Do applications for payment run inside Archdesk?

Yes. Applications for payment run against the same cost codes the WIP and the CVR read from, with payment certification on the same records, so the certified position and the billing position always agree.

Does Archdesk integrate with the accounting systems Irish contractors use?

Yes. Archdesk is a certified Xero partner and integrates with Sage, so the commercial record and the ledger stay in step without re-keying.

See your next project on Archdesk

Book a demo and walk through a fully worked example project: one platform running everything from winning the work to closing it out.

Book a Demo
Archdesk rating on Software AdviceArchdesk rating on CapterraArchdesk rating on GetApp