Site teams spend about 30% of their week, roughly 12 hours, searching for documents. Document control fixes that waste and it stops the bigger loss, building to the wrong revision and paying for rework, delay, and disputes. You’ll leave with a simple way to set up a Common Data Environment (CDE), run a register, issue revisions with transmittals, and prove who had what, when.
In this article
Wrong revision, real cost
Situation
A 45-strong mechanical contractor in South London, about £18m turnover, mostly Cat A and Cat B office fit-out. They were on a £280k first-fix package for heating and chilled-water pipework on a £3.8m Cat B refurbishment. The programme was 16 weeks and ceilings had to close on floor two in week 6.
Files were “controlled” through email, a shared folder, and whatever was printed in the site office. No live drawing register existed on site.
What happened
Week 4, the architect issued revised coordination drawings. A chilled-water riser moved 600mm to clear a new structural beam. Rev P3 went out on a transmittal to the main contractor’s project manager. Rev P2 stayed pinned on the site office wall.
Five days followed where everyone did what they thought was right. Pipefitters installed 38 metres of chilled-water pipework to Rev P2. Brackets, fire-stop sleeves, and builder’s work holes all landed in the wrong line. Nobody checked a register because there wasn’t one, and the site team had no single place to confirm “this is the current drawing”.
Day six, a ceiling-void walkdown spotted the clash. Strip-out and re-install took eight working days. Labour cost £9,200. Wasted materials were £3,400. The bigger hit was the knock-on, drylining could not close the ceiling on floor two, so they ran six extra days of prelims at £1,100 a day and claimed £6,600 loss and expense. Total cost of one wrong revision was £19,200 on a £280k package.
The mechanical contractor tried to push the cost up the chain. The main contractor asked for one thing, the formal issue record showing when Rev P3 was sent to the mechanical site team. Nobody could produce it. All they had was an email thread and a photo of the old drawing on the wall.
The decision / the lesson
The fix was basic and it stuck because it was enforceable. They put one named document owner on the package and introduced three rules the next Monday.
- Register every issue. Each drawing goes on a register with drawing number, current revision, date received, and transmittal reference.
- Check before you start. The foreman checks the register before starting any new area, even if a drawing is pinned up.
- Kill superseded drawings fast. Old revisions come off the wall within 24 hours. The digital copy is clearly marked “SUPERSEDED” so nobody can open it and assume it’s current.
Those steps took about 20 minutes a week to maintain. They stopped “wrong-revision installs” because the team could prove what was current before labour hit the deck. They also cut the dead time spent hunting for drawings. Site staff typically lose about 30% of their week, roughly 12 hours, searching for or checking documents. That wasted time is where wrong revisions slip through.
Document control, defined
Document management is storing and sharing project files, document control is the rules that make one approved version the only one anyone builds from.
Think of it like a cheque book. Storing the cheque stubs is management. Control is knowing who can sign, what value they’re allowed to sign for, and having a record you can prove later.
- Document management
- Storing, organising, and sharing project files so people can find them. It answers, “Where is the file?”
- Document control
- The rules, approval steps, and audit trail that govern a file from draft to archive. It answers, “Is this the right file to build from, and can I prove it?”
- Common Data Environment (CDE)
- The single controlled place where the project team stores and issues project information, so there is one agreed current version of each drawing, spec, RFI and record.
- Audit trail
- A time-stamped history of actions on a document, who uploaded it, changed it, approved it, issued it, and when.
Poor control turns into rework fast. On a £1.2m Cat B fit-out over 16 weeks, one wrong-revision install, like an electrician setting containment off an old reflected ceiling plan, regularly creates £15,000 to £25,000 of abortive work and re-sequencing, before you even start the argument about who pays.
Four states, one truth
Only build from documents in the Published state, because that’s the only label that proves the team has checked and approved what you’re about to install.
Think of it like a commercial kitchen. Prep food stays in the prep area, plated food sits on the pass waiting for the chef’s check, “service” food goes to customers, and yesterday’s batch goes into storage for traceability. Nobody serves food from prep, and nobody should build from a draft drawing.
- Work in Progress (WIP)
- Draft information still being developed by the author. Nobody outside that author team should build, order, or set out from it.
- Shared
- Issued for review and comment. The wider team can coordinate and mark up, but it is not approved for construction.
- Published
- Approved for construction use. This is the only state you treat as “the truth” for procurement, setting out, and installation.
- Archived
- Superseded or completed information kept as the record for audit, final account, and claims. Searchable, but never current.
A single “wrong-state” build can become a real money problem fast. A £40,000 M&E rework dispute is usually not about technical ability, it’s about proving what revision each party had on the day the work was done. If you can’t show when a drawing moved from Shared to Published, you end up paying for fixes you shouldn’t.
Official issue, not email
An official issue is a drawing or spec you can prove was sent, received, and at what revision.
Think of it like posting a parcel. Dropping it in a postbox moves it, but you can’t prove it arrived. Tracked delivery with a signature is proof. A transmittal is the tracked-delivery receipt for construction documents.
- Version
- Any saved iteration of a file, including drafts and internal edits. Versions are working history, not a green light to build.
- Revision (Rev)
- A controlled, numbered change to a drawing or specification that has been checked and approved for issue, like Rev 02 to Rev 03. The revision tells site which update they are building from.
- Transmittal
- A formal issue sheet that records exactly what was sent, sheet by sheet, including document number, title, revision, date, sender, recipients, and a transmittal number. This is what makes an issue defensible later.
- Drawing register
- A live list of every drawing sheet on the job showing the current revision and status, plus the last transmittal it was issued under, so teams can check what is safe to build from.
One wrong drawing revision can wipe out a week’s margin. On a £1.2m fit-out, an MEP crew building ductwork to Rev 02 instead of Rev 03 can trigger a £12,000 to £15,000 rework weekend and lose a week on the programme, then turn into an argument nobody can win because nobody can prove who had what.
drafting with 3 models in parallel
Build your first register
Setting: a £1.2m Cat-B office fit-out, JCT Design and Build, 16-week programme. It’s week 2, trades are on site, and you already have 62 live files scattered across email chains and shared folders. You need a starter register that tells the team what exists, what state it’s in, and what is safe to build from.
Mechanics, step by step
-
Create six buckets that match site work, then give each a Doc ID prefix. The prefix stops “ceiling plan final FINAL.pdf” becoming your control system. On this job, your week 2 snapshot looks like this.
Bucket What goes in it Doc ID prefix Week 2 count Drawings and specs Drawings and specifications, the written requirements DRG 18 Submittals Shop drawings and product data for approval SUB 11 RFIs RFIs, Requests for Information, formal questions RFI 6 Change management Variation records, changes that affect time or money VAR 4 Field records Daily diaries, inspections, snagging logs, defect lists FRM 19 Closeout Handover pack, O&Ms, warranties, as-builts CLS 4 -
Build the register with ten columns, then never change them mid-job. Changing columns in week 9 breaks filtering, reporting, and audit trail.
Column Example value Why it matters Doc ID DRG-017 Every argument ends at one reference. Doc type Drawing Fast filtering by what the team needs. Title Level 02 reflected ceiling plan Search works for site staff, not just designers. Package Ceilings Maps to trade scope and procurement. ISO state Published Shows if it’s safe to build from. Rev P03 Stops rework caused by silent drawing changes. Owner Design Manager One named person to chase. Due date Wk 3 Mon Stops approvals drifting into the critical path. Transmittal no. T-005 Proof of what was issued, to whom, and when. Link /Published/DRG/DRG-017_P03.pdf Keeps the team off email attachments. -
Enter live documents using the four-state model. Work in Progress is draft. Shared is issued for review. Published is approved for construction use. Archived is retained for history and claims.
Doc ID Bucket ISO state Rev Transmittal Build from it? DRG-017 Drawings and specs Published P03 T-005 Yes DRG-018 Drawings and specs Shared S01 T-006 No SUB-004 Submittals Shared S02 T-007 No, don’t order until approved RFI-003 RFIs Shared S01 T-008 No, answer outstanding VAR-002 Change management Work in Progress W01 N/A No, not agreed -
Issue one “official” transmittal, then archive the superseded revision the same day. Example: Transmittal T-005 includes 7 sheets, including DRG-017 Rev P03, and goes to 9 recipients (ceiling foreman, M&E supervisor, setting-out engineer included). DRG-017 Rev P02 moves to Archived within 30 minutes of issue so nobody prints it again on Friday afternoon.
Takeaway
The non-obvious bit is that “ISO state” and “Transmittal number” turn document control into a build/no-build decision. A ceiling gang installing off DRG-018 in Shared state can burn £4,860 of labour in a day, then you pay twice when it has to come down and go back up. Your register prevents that by making “Published under T-xxx” the only answer the site accepts.
Name files, find fast
A £1.2m Cat-B office fit-out in Leeds, JCT Design & Build, 16-week programme. Week 4, the architect issues a revised core layout and the M&E subcontractor updates a ceiling coordination drawing after RFI 014 clears a clash. Two supervisors both download “the latest”, but one prints an older PDF because the filenames don’t sort or search the same way.
Worked example: one rule, plus one exception
-
Start with one naming rule for most documents. Use: ProjectName_DocumentType_Title_Date. Keep the order fixed and split with underscores so sorting works the same for everyone.
Example for the core layout: LeedsHQ_DRG_CoreLayout_20260601.pdf.
-
Add a revision tag only for “living” documents. Drawings and submittals change, so add _Rev01, _Rev02, etc. Don’t use “FINAL” or “NEW”. They are opinions, not control.
Example for the ceiling coordination update: LeedsHQ_DRG_CeilingCoordination_20260610_Rev03.pdf.
-
Keep document type codes short and closed. If you allow people to invent codes, you lose the whole point. Pick a small set and stick to it.
| Document | What people call it without a rule | Correct filename | Why it works |
|---|---|---|---|
| Architect drawing, revised | Core layout FINAL v2 NEW.pdf | LeedsHQ_DRG_CoreLayout_20260601_Rev03.pdf | “DRG” + title finds it fast, “Rev03” tells you what to build |
| M&E shop drawing | M+E riser detail (use this one).dwg | LeedsHQ_SUB_RiserDetail_20260608_Rev01.dwg | “SUB” separates submittals from design drawings, revision is clear |
| RFI response record | RFI answer latest.pdf | LeedsHQ_RFI_014_CeilingVoidClash_20260610.pdf | RFI number anchors the thread, no revision needed |
Date-first naming, only for time-series
-
Flip to date-first only when you search by date. Daily diaries, permits, inspection logs, and site reports are time-series. You don’t search those by title. You search “what happened on 11 June”.
Use: YYYYMMDD_ProjectName_DocumentType_Title. Example: 20260611_LeedsHQ_RPT_DailyLog.pdf.
-
Prove the rule works with a 20-second test. Ask the site manager to find the latest ceiling coordination drawing by searching “CeilingCoordination”. Ask the QS to find it by filtering “LeedsHQ” + “DRG”. Both should land on LeedsHQ_DRG_CeilingCoordination_20260610_Rev03.pdf first time.
Takeaway
Most teams think the date is what makes a file “latest”. Revision control is what makes it safe to build from. Date-first naming is not “better”. It only fits time-series records where the date is the primary way you search, like daily reports and permits. Everything else wants a fixed pattern that sorts and searches the same way for every person, every time.
Permissions you can prove
This checklist diagnoses whether your Common Data Environment (CDE, your single controlled place for project information) has permissions you can defend in a dispute, audit, or final account query. Tick what is actively enforced on your live job, not what's written in a procedure.
- A named Document Controller exists, even if it's a part-time role under the PM.
- Your permissions matrix is written down, roles across the top and the four states down the side: Work in Progress, Shared, Published, Archived.
- Every file in the CDE sits in one of those four states, with no "misc" folders acting as a fifth state.
- Work in Progress is editable only by the authoring team, and it's not visible to site operatives or subcontractors.
- Design disciplines can only edit their own Work in Progress, not each other's.
- Shared is editable only by the Document Controller and named PM staff. Everyone else is ReadOnly.
- Published is ReadOnly for everyone, including the PM and Document Controller. Nobody can "tidy up" a Published file.
- External parties can only upload into a controlled intake area or Work in Progress. They cannot edit Shared or Published.
- The system logs who uploaded, moved state, approved, viewed, and downloaded, with timestamps you can export.
- Superseded Published drawings are moved to Archived the same day the new revision is Published, and the drawing register is updated to match.
- A weekly 30-minute register review happens with the PM, QS (Quantity Surveyor, the commercial lead), and Document Controller. Anything stuck in Shared for more than 7 days gets an owner and a due date.
- A monthly spot-audit happens. Pick 10 random Published files and prove the approval record, the transmittal, and the register revision all match.
Reading the result: 0–4 ticks: you're running a shared drive with nicer branding. Lock Published and appoint ownership before the next drawing issue. 5–8 ticks: the structure is there, but trust will break the first time a late change hits. Fix Shared editing rights, the audit trail, and the weekly review. 9–12 ticks: your role-to-state permissions matrix is defensible, and your cadence will stop wrong-revision work before it reaches site.
Fill-in template: role-to-state permissions matrix
Copy this table into your project execution plan. For a £4.8m office fit-out with an M&E subcontract package, here's a worked example filled in alongside blank cells for your own job. "E" means Edit, "R" means ReadOnly, "N" means No Access, "U" means Upload Only.
| CDE State | Document Controller | PM / Contracts Manager | Design Lead (per discipline) | QS | Site Manager / Foreman | Subcontractor (e.g. M&E) | Client Rep | Your Job: ___________ |
|---|---|---|---|---|---|---|---|---|
| Work in Progress | E | R | E (own discipline only) | N | N | U (intake folder only) | N | |
| Shared | E | E | R | R | N | N | R | |
| Published | R | R | R | R | R | R | R | |
| Archived | R | R | N | R | N | N | R |
Two things to notice in the worked example. The M&E subcontractor gets Upload Only into WIP, not Edit. That stops them overwriting the design lead's coordination model. Site managers get ReadOnly on Published only, nothing else. If they need a drawing, it's the correct issued revision or nothing.
Fill-in template: weekly control cadence
This is the actual meeting agenda and action loop that makes the matrix stick. Below is a worked example for the same £4.8m fit-out, with blank rows so you can adapt it.
| Day / Time | Action | Who | Output | Your Job: ___________ |
|---|---|---|---|---|
| Monday AM | Document Controller runs a "stuck in Shared" report: any file in Shared state for 7+ days. | Document Controller | List of stale files with original upload date. | |
| Monday PM | PM assigns an owner and a 48-hour deadline to each stale file: approve to Published or reject back to WIP. | PM | Updated register with named owners and due dates. | |
| Wednesday AM | Document Controller checks all superseded Published files have been moved to Archived and the drawing register revision column matches. | Document Controller | Clean register, zero orphaned revisions. | |
| Thursday PM (30 mins) | Register review meeting. PM, QS, Document Controller review: files moved to Published this week, outstanding RFIs blocking approvals, any subcontractor uploads needing design-lead review. | PM, QS, Document Controller | Meeting note with three columns: Approved, Rejected back to WIP, Escalated to design lead. | |
| Friday AM | Site Manager confirms site drawing packs match the latest Published register. Flags any mismatch to Document Controller before the weekend. | Site Manager | Confirmation email or logged check on site diary. | |
| Last Friday of month | Spot-audit: pick 10 Published files at random. Verify each has a matching transmittal, an approval record, and the correct revision in the register. | QS + Document Controller | Audit log with pass/fail per file. Any fail gets a corrective action within 5 working days. |
On one £6.2m residential scheme in Birmingham, a contractor ran this cadence for 22 weeks straight. During final account negotiations, the QS pulled the audit logs in under 10 minutes and proved every published drawing matched the transmittal record. The client's QS dropped two of three disputed variation queries on the spot, worth £74k, because the revision trail was clean. That's what a defensible cadence buys you. In Archdesk, the document control module tracks state, revision, and transmittal with a timestamped audit trail, so the Thursday register review pulls a live "stuck in Shared" list and the monthly spot-audit data straight from the system instead of a manual spreadsheet trawl.
Process an RFI cleanly
Try this: You are the document controller for a £1.2m, 12-week Cat B office fit-out. Your drylining subcontractor spots a clash between a ceiling bulkhead and a smoke detector shown on the reflected ceiling plan. The supervisor sends you a marked-up phone sketch at 15:40 on Tue 10 June 2026 and asks, "Which takes priority, and can we move the detector 300mm?" You must raise and run RFI-014 (Request for Information, a formal question that can affect time and cost) so there is one traceable thread from question to answer, and it links to the drawing revision and any variation (a contract change that affects time or money).
| Item | Input you must use |
|---|---|
| RFI number | RFI-014 |
| Package | Drylining (discipline impact: M&E) |
| Drawing referenced in the question | ACMEHQ_DRG_A-152 Reflected Ceiling Plan, Rev 03, dated 20260603 |
| Marked-up sketch received | Phone photo with annotation, treat as Work in Progress |
| Response due date rule | 7 calendar days from issue |
| People who need it | Architect, M&E subcontractor, Site Manager, Drylining supervisor |
| Access rule | Site operatives must only see Published drawings |
| Designer response arrives | 15:10 on Mon 16 June 2026, "Move detector 300mm. Issue revised RCP." |
| Revised drawing arrives | ACMEHQ_DRG_A-152 Rev 04, dated 20260616 |
| Commercial flag | M&E says the move will cost £450 and needs client approval |
Write the workflow you will follow from intake to archive. Use the four ISO 19650 states: Work in Progress, Shared, Published, Archived. At every step, show the RFI status value, the document suitability code, and who received the issue. Your end result must prove who asked, who answered, what drawing changed, who received it, and how you stopped the gang building off Rev 03.
Show the worked solution
RFI register entry you create at Step 1
| Field | Value |
|---|---|
| RFI No. | RFI-014 |
| Title | Bulkhead clash with smoke detector, RCP A-152 Rev 03 |
| Status | Open |
| Priority | Programme-critical (hold on setting-out) |
| Originator | Drylining supervisor (J. Barr) |
| Package | Drylining |
| Discipline impact | M&E |
| Linked drawing | ACMEHQ_DRG_A-152 Rev 03 (20260603) |
| Issue date | 10 Jun 2026 |
| Due date | 17 Jun 2026 |
| Ball in court | Architect |
| Internal reviewer | Site Manager |
| Variation link | None yet |
Step-by-step workflow
Step 1, Log the query (RFI status: Open). Create the register entry above. Every field matters at final account. "Ball in court" drives your chase list. "Internal reviewer" means the answer gets checked for buildability before you close it out.
Step 2, File the sketch as evidence (document state: Work in Progress, suitability S0). Save the phone sketch as 20260610_ACMEHQ_RFI-014_SiteSketch_WIP.pdf. Mark suitability S0 (Work in Progress, not for construction). Lock access so site operatives cannot see it. This sketch is evidence, not instruction.
Step 3, Draft and issue the formal RFI (RFI status: Issued, document state: Shared, suitability S1). Write the question as one clear ask: "Confirm priority between bulkhead and smoke detector. Confirm whether detector can move 300mm and any fire-strategy implications." Attach the WIP sketch and reference A-152 Rev 03. Change the RFI document state to Shared (S1, suitable for coordination). Issue through the CDE (common data environment, your single controlled document store) so the system captures recipient names, email addresses, and timestamps automatically.
Transmittal record for the RFI issue
| Transmittal field | Value |
|---|---|
| Transmittal No. | TX-041 |
| Date/time sent | 10 Jun 2026, 16:15 |
| Document issued | RFI-014 + sketch attachment |
| Issued to | Architect (K. Patel, k.patel@archco.com), M&E sub (D. Reeves, d.reeves@mecsystems.co.uk), Site Manager (N. Collins), Drylining supervisor (J. Barr) |
| Action required | Architect: respond by 17 Jun 2026. All others: for information. |
| Acknowledgement received | K. Patel 16:22, D. Reeves 16:45, N. Collins 16:18, J. Barr 16:50 |
Record every acknowledgement timestamp. On a disputed variation six months later, this table proves the architect received the question on 10 June and was given seven days.
Step 4, Hold site work while the RFI is open. Add a site instruction note against RFI-014: "Hold setting-out of bulkhead at gridline G3-G5 until RFI-014 is closed." Flag A-152 Rev 03 on the drawing register with "Open RFI-014" so nobody treats it as settled.
Step 5, Log the response (RFI status: Answered – Awaiting Revised Drawing). The designer responds at 15:10 on Mon 16 June 2026. Upload the response against RFI-014 and paste the response text into the register's "Response" field. Change status to "Answered – Awaiting Revised Drawing." This intermediate status tells the team: you have an answer but no drawing to build from yet.
Step 6, Receive and check the revised drawing (document state: Shared, suitability S2). Upload ACMEHQ_DRG_A-152 Rev 04 (dated 20260616) into Shared at suitability S2 (suitable for information). Check the detector is shown moved 300mm and the change is clouded. Only after your check, move Rev 04 to Published at suitability S4 (suitable for construction).
Step 7, Distribute and close (RFI status: Closed). Issue Rev 04 via a new transmittal (TX-042). The transmittal must list the drawing number, revision, date, and every recipient with their acknowledgement time.
| Transmittal field | Value |
|---|---|
| Transmittal No. | TX-042 |
| Date/time sent | 16 Jun 2026, 16:30 |
| Documents issued | ACMEHQ_DRG_A-152 Rev 04 (S4, Published) + RFI-014 close-out notice |
| Issued to | Architect, M&E sub, Site Manager, Drylining supervisor |
| Reason for issue | Revised drawing per RFI-014 response. Supersedes Rev 03. |
Close RFI-014. Final status: Closed. The RFI document itself moves to Published (the answer is now approved information the team can act on).
Step 8, Archive the superseded revision. Move ACMEHQ_DRG_A-152 Rev 03 to Archived. Add metadata note: "Superseded by Rev 04 on 20260616 per RFI-014." If paper sets exist on site, instruct the Site Manager to pull Rev 03 the same day and replace it with Rev 04. Log the paper swap in the daily site diary with a time.
Step 9, Link the money thread. Open a variation record: "Smoke detector relocation 300mm, £450." Link it to RFI-014 and to drawing Rev 04. The M&E sub's £450 claim now has a traceable chain: RFI question, designer response, revised drawing, transmittal receipt. This stops it being waved away as a site fix at final account.
Completed RFI register row after close-out
| Field | Final value |
|---|---|
| RFI No. | RFI-014 |
| Title | Bulkhead clash with smoke detector, RCP A-152 Rev 03 |
| Status | Closed |
| Originator | Drylining supervisor (J. Barr) |
| Date raised | 10 Jun 2026 |
| Date issued | 10 Jun 2026, 16:15 (TX-041) |
| Due date | 17 Jun 2026 |
| Date answered | 16 Jun 2026, 15:10 |
| Date closed | 16 Jun 2026, 16:30 |
| Days open | 6 |
| Response summary | Move detector 300mm. Issue revised RCP. |
| Drawing superseded | ACMEHQ_DRG_A-152 Rev 03 → Archived |
| Drawing issued | ACMEHQ_DRG_A-152 Rev 04 → Published (S4) |
| Variation link | VAR-009, £450, pending client approval |
| Close-out transmittal | TX-042 |
What most people get wrong: they publish Rev 04 but leave Rev 03 live in the Published set. The gang builds off the wrong revision, and the £450 variation turns into a £3,000 abortive-works argument at final account. The second common mistake is recording only two statuses, Open and Closed, with no intermediate state. That hides the gap between "designer answered" and "revised drawing checked and issued." If site acts on the email response before Rev 04 is Published, you have no controlled instruction to point to if it goes wrong.
Kickoff to closeout, controlled
Document control works when one agreed system tells every trade what is safe to build from, and proves who saw what and when. Below is a worked one-page plan you can copy and adapt for your next pre-start meeting.
One-page document control plan: worked example
Project: Acme HQ Fit-Out, £4.2m Cat B, 22 weeks
Document controller: Sarah Patel (single named owner)
CDE rule: ISO 19650 four-state model. No file lives outside this structure.
Folder map (mirror in your CDE exactly)
| ISO state | Folder path | What lives here |
|---|---|---|
| S1, Work in Progress | /ACMEHQ/S1-WIP/[Trade]/[DocType] | Drafts, mark-ups, internal sketches. Not for construction. |
| S2, Shared | /ACMEHQ/S2-SHARED/[Trade]/[DocType] | Issued for comment, coordination, or design review. |
| S3, Published | /ACMEHQ/S3-PUBLISHED/[Trade]/[DocType] | Approved for construction. The only state site should build from. |
| S4, Archived | /ACMEHQ/S4-ARCHIVED/[Trade]/[DocType] | Superseded revisions, closed-out records. Never delete, only move here. |
Trade subfolders: M&E, Partitions, Ceilings, Joinery, Façade, Structural, Architectural. DocType subfolders: DRG (drawings), SPEC, RFI, TRANSMITTAL, SCHEDULE, O&M, TEST-CERT.
Register fields (minimum set, non-negotiable)
| Field | Example entry |
|---|---|
| Doc ID | ACMEHQ-DRG-0041 |
| Title | Level 3 Core Layout |
| Revision | Rev 03 |
| ISO state | S3, Published |
| Date issued | 01 Jun 2026 |
| Transmittal ref | TRN-027 |
| Originator | WSP (architect) |
| Received by | M&E sub, drylining sub, PM |
| Linked RFI / variation | RFI-019 → VAR-006 |
| File link | /S3-PUBLISHED/Architectural/DRG/ACMEHQ_DRG_CoreLayout_20260601_Rev03.pdf |
Naming convention, enforced without exception: ProjectCode_DocType_Title_YYYYMMDD_Rev##.pdf
Transmittal rules (paste these into your project preliminaries)
- Published documents are issued by formal transmittal only. No email attachments, no WhatsApp photos.
- Every transmittal lists each document by Doc ID, title, revision number, and ISO state.
- The recipient confirms receipt within 48 hours. No confirmation = chaser at 72 hours, escalation to PM at 96 hours.
- Superseded drawings move to S4-Archived on the same day the new revision enters S3-Published. The transmittal notes which revision is replaced.
Permission matrix by ISO state
| Role | S1, WIP | S2, Shared | S3, Published | S4, Archived |
|---|---|---|---|---|
| Doc controller (Sarah) | Edit | Edit | Edit (sole gatekeeper) | Read only |
| Design team leads | Edit (own trade) | Edit (own trade) | Read only | Read only |
| Site managers / foremen | No access | Read only | Read only | No access |
| Subcontractor PMs | No access | Read only (own trade) | Read only (own trade) | No access |
| Client / CA | No access | Read only | Read only | Read only |
The rule that matters most: Published is read-only for everyone except the document controller. No exceptions.
Closeout timeline (dated milestones)
| Milestone | Week (of 22) | Action |
|---|---|---|
| Kickoff | Week 1 | Open closeout register. List every O&M manual, warranty, test cert, and as-built required. Assign responsible trade. |
| Mid-job audit | Week 11 | Audit closeout register: chase missing certs and warranties for completed packages. Flag gaps in weekly PM meeting. |
| Pre-PC push | Week 18 | 80% of closeout pack complete. Outstanding items on a named punchlist with deadlines. |
| Practical completion | Week 22 | Full O&M pack, all as-builts, all test certs handed to client. Final register export to separate backup storage. |
| Monthly (ongoing) | Every 4 weeks | Export full register and file set to separate storage. One cloud copy is not a backup. |
What to learn next
- RFI and variation traceability, because one RFI (Request for Information) can trigger a revised drawing and a variation. You need one chain you can price and defend.
- Field mark-ups and as-builts, because if site changes stay on paper and WhatsApp, you will rebuild the record from memory at handover.
- Closeout pack structure for FM users, because O&Ms filed by trade suit builders, but facilities teams search by asset and location. The wrong structure delays sign-off and final payment.
Most rework starts with the wrong revision, not bad workmanship. A plumber installing to Rev 02 when Rev 03 was issued two weeks earlier is a fast route to £15,000 of abortive work and an argument nobody wins. Run the plan inside your CDE and keep it boring and enforced. In Archdesk this is the CDE setup with role-based permissions, version history, and approval workflows, so Published files are locked and every transmittal is time-stamped for audit and claims.
Frequently Asked Questions
What is the difference between document management and document control in construction?
Document management is storing and sharing project files. Document control is the set of rules that makes one approved revision the only version anyone builds from. Without control, you end up with multiple copies of the same drawing in email threads and shared folders, and no proof of who worked from what. On a typical 16-week fit-out with 60+ live files by week 2, that distinction is the difference between a clean programme and a rework claim.
How much does a wrong drawing revision actually cost on a construction project?
On a £280k mechanical package inside a £3.8m Cat B refurbishment, a single superseded revision reaching site can trigger abortive pipework, ceiling delay, and a re-sequencing cost that dwarfs the original labour. The direct rework is only part of it. The knock-on, such as a ceiling close-out slipping from week 6, compounds across every follow-on trade and can turn a contained package loss into a programme-wide problem.
What are the four document states in a Common Data Environment and which one is safe to build from?
The four states are Work in Progress, Shared (for review), Published (approved for use), and Archived. Only build from documents in the Published state, because that is the only label that proves the team has checked and approved the content. Anything still marked Shared or Work in Progress has not passed its approval gate. Treating a Shared drawing as buildable is one of the most common causes of abortive work on site.
How should I set up a document register for a small fit-out project?
Start with six buckets that match how site work actually flows, such as architectural, structural, M&E, subcontractor submittals, RFIs, and project admin. For a £1.2m Cat B office fit-out under JCT Design and Build, you'll typically have around 62 live files by week 2. Each entry needs a unique reference number, current revision, document state, and issue date. That register becomes your single source of truth for what exists, what's approved, and what's safe to install from.
What file naming convention works on construction projects to stop people printing the wrong drawing?
Use a structured name that sorts and searches predictably: project code, originator, zone or level, drawing type, sequence number, then revision. For example, ACME-ARC-L02-DR-0401-P03 tells you the project, that it's an architect's drawing, it covers level 2, and it's at revision P03. When two supervisors both download "the latest" but filenames don't sort the same way, the wrong PDF gets printed. A consistent convention kills that problem at source.
How do I process an RFI properly so it doesn't slow the programme or create a dispute?
Log the RFI with a unique number, the exact question, who raised it, and the date and time received. Set a response deadline tied to the programme, typically 3 to 5 working days on a 12-week fit-out. Track the answer back to a specific drawing revision and update the register so the response links to the document it changes. If you can't show the audit trail from question to revised drawing to site issue, you'll struggle to defend a variation claim or prove delay responsibility at final account.
What CDE permissions do I need to defend my position in a contract dispute or final account?
You need a named document controller, even if it's a part-time role under the PM. Every user must have role-based access so you can prove who could view, edit, or approve each file. Your CDE must log every upload, download, and status change with a timestamp. If your audit trail can't show that a subcontractor received revision C before they started work, your contractual position under JCT or NEC weakens to the point where proving responsibility becomes almost impossible.
What should a one-page document control plan include for a pre-start meeting?
Name one document controller as the single owner. State the CDE platform and confirm that email is not a valid issue route. Set the naming convention, the revision numbering format, the approval workflow, and the response deadlines for RFIs. On a £4.2m, 22-week Cat B project, this one-page plan goes into the pre-start pack so every trade signs up to the same rules before they mobilise. If it's not agreed at kickoff, you'll spend the rest of the job arguing about what was issued and when.
![Best 15 Subcontractor Management Software for 2026 [Quadrant]](/_next/image?url=%2Fapi%2Fblog-posts%2Ffile%2Fbest-subcontractor-management-software-archdesk-1200x800.jpg&w=3840&q=75&dpl=dpl_24rtWSGpb1bvJFDhcPctEQRyehfS)




