Congratulations on building a successful business! Most don't get that far. Often times, we see the push from £5M to £10M-£15M is the hardest. As the saying goes, What got you here, won't get you there. Most fit-out firms that jump from £5m to £15m don’t fail on site, they fail in cash, because they grow turnover faster than they shorten the payment cycle. £15m in 12 to 18 months is a maths problem and a control problem. You need enough starts per month, enough delivery capacity, and tight commercial admin so you don’t fund your own projects. You’ll leave with a simple model, weekly rules, and a 90-day plan you can run with your team.
Quick answer
Grow from £5m to £15m by controlling three numbers every week: starts per month, live workload per PM and QS, and cash gap from valuation to payment. Default plan is 1 to 2 starts a month at £600k to £900k, with weekly CVR (cost value reconciliation) and a variation log that gets scope, price, and status agreed inside 14 days. The key exception is cash, if your payment terms are slow or retention is heavy, you must either shorten the cycle or ring-fence working capital before you add starts.
- Set a starts target and refuse work that breaks delivery capacity, one PM per £2m to £3m live workload is a safe rule of thumb.
- Run weekly CVR and triggers, fix reds before Friday, don’t wait for month end to discover margin has gone.
- Stop variation drift, log and price weekly, chase certification to the next valuation date or you fund the job.
In this guide
Model £15m in numbers
£15m turnover is a maths problem, not a motivation problem. You need four numbers: average job value, starts per month, win rate, and how many live jobs your team can control at once.
Think of turnover like water through a hose. More flow needs a wider hose (delivery capacity) and tighter joints (less leakage from prelims creep, unpaid variations, and retention drag).
- Programme
- The planned sequence and dates for the job from mobilisation to Practical Completion, usually shown week by week.
- Prelims (Preliminaries)
- Site running costs not tied to one trade, like the Site Manager, welfare, hoarding, temporary power, skips, security, and supervision.
- Variation
- A change to the agreed scope that must be priced and agreed, then picked up in your valuation.
- Retention
- Money held back from each payment, usually part released at Practical Completion and the balance after the Defects Liability Period (the snag-fix period after handover).
The one-page model (worked example)
Use round numbers so you can sanity-check the plan in your head. Example: Cat A or Cat B fit-out averaging £750k with a 12-week programme and a 25% win rate.
- Annual target: £15m.
- Average job value: £750k.
- Jobs needed per year: £15m ÷ £750k = 20 jobs.
- Starts per month: 20 ÷ 12 = 1.7. Plan for 2 starts per month because some starts slip.
- Live delivery load: 12 weeks is about 3 months, so 2 starts per month means 6 live jobs at once.
- Tenders needed: 2 starts ÷ 25% win rate = 8 tenders per month, about 80 tenders per year.
- Pipeline value: 80 tenders × £750k = £60m+ of priced work to feed the year.
Missing the starts number bites harder than most owners expect. One start per month at £750k lands at roughly £9m turnover for the year. You still carry the overhead you hired to run £15m.
Build leads and pipeline
Setting: you run a UK commercial Cat B fit-out contractor turning over £5.2m. Your plan is £15m turnover inside 12 to 18 months, with an average contract value of £742,000 and a 25% tender win rate. Site delivery won’t be the first thing that breaks, the diary will, because you run out of priced work or you drown your estimators in dead-end tenders (a price and proposal you submit).
| Pipeline maths | Target | What it forces |
|---|---|---|
| Turnover target | £15,000,000 | Plan a 12-month rolling pipeline, not “contacts”. |
| Average contract | £742,000 | 20.2 wins per year (about 1.7 wins per month). |
| Win rate (wins ÷ tenders) | 25% | 80.8 tenders submitted per year (6 to 7 per month). |
| Hit rate (tenders ÷ enquiries) | 50% | 161.6 enquiries per year (13 to 14 per month). |
| Total enquiry value needed | £60,000,000 | Enough work “in the hopper” to keep starts steady. |
| Weekly enquiry value | £1,250,000 (48-week year) | About 1.7 real enquiries per week, every week. |
-
Split the £60m target into channels so one route can’t starve you. Set a mix you can actually manage: £24.0m via Main Contractors, £24.0m direct Employers (the client paying for the works), and £12.0m via consultants (PMs and QSs who influence tender lists).
That sets weekly targets of £500k Main Contractor-led, £500k direct Employer, and £250k consultant-led enquiries.
-
Define what counts as a “real enquiry”, or your numbers lie to you. A real enquiry has a budget range, a decision date, and a route to tender (how you get invited). Rule: if you can’t capture all three inside 10 minutes, log it as marketing, not pipeline.
This stops “nice chats” inflating your forecast by £5m to £10m on paper, then turning into nothing in the diary.
-
Run a bid no-bid within 24 hours, using a hard gate. Score the lead out of 10. Only bid at 7+.
Example for a £896,400 Cat A office refurb: budget confirmed (2), start on site within 12 weeks (2), decision maker named (2), drawings at RIBA Stage 4 level (2), and you have delivered for that Main Contractor or Employer before (2). A score of 6 means decline the same day.
-
Turn the annual target into weekly actions you can hold people to. You’re aiming to create £1.25m of real enquiries per week, not “be busy”.
Weekly cadence that matches the channel split: 12 calls to Main Contractor commercial managers or pre-construction leads, 10 calls or emails to direct Employers, and 3 consultant meetings or warm introductions. Total: 25 outbound actions to find 1 to 2 real enquiries.
-
Use a 10-minute qualification script that forces dates and money onto the table. Ask in this order, and write the answers down.
1) “What’s the budget range?” 2) “What’s the tender return date?” 3) “Who signs the order?” 4) “What form of contract, JCT or NEC?” 5) “How many tenderers are you inviting?” 6) “Are there any PC Sums or Provisional Sums?” 7) “Who is the QS valuing work and agreeing variations?” If they dodge two of these, you walk away.
-
Attach a dated next step to every live lead, or park it. A next step is a calendar entry, not a promise.
Example: “Tender pack issue Fri 14th. Scope review call Mon 17th 09:00. Site visit Wed 19th 07:30.” No dates means no estimating hours.
Takeaway: the hidden constraint is estimating capacity, not marketing spend. 81 tenders a year at 23 hours each is 1,863 estimating hours, before site visits and sub-contractor chase. That is 1.1 full-time people at 35 hours per week. The pipeline maths tells you, in black and white, you must either hire a second estimator or increase your “no” rate. If you track this in Archdesk, the bid management workflow makes the no-bid gate, next-step dates, and tender workload visible in one place, so the funnel doesn’t empty while everyone feels busy.
Master the payment cycle
Cashflow in fit-out is a conveyor belt. Growth means more cash stuck on the belt unless you shorten the time from valuation to money in bank.
- Valuation date
- The monthly cut-off for measuring work done and submitting your application for payment.
- Interim Certificate
- The certificate issued by the Contract Administrator stating what must be paid for that period.
- Final date for payment
- The last contractual date the payer can pay the certified sum without being in breach, usually set days after the Interim Certificate under JCT.
- Payless notice
- A formal notice under the Construction Act reducing what will be paid. Weak or late backup makes it easy for the payer to serve one.
The worked example: a £750k Cat B office fit-out, 12 weeks
You need a simple week-by-week table that plots cash out against cash in. Build it in a spreadsheet with four columns: Week, Cumulative spend, Cumulative cash received, and Net cash position. Here is how the maths works for this job.
Assumptions: total contract value £750k. Weekly spend is roughly even at £62.5k. Valuation happens at week 4, then every 4 weeks. The Contract Administrator issues the Interim Certificate 5 days after each valuation. Payment lands 21 days after certification. Retention is 5% of each certified sum. So for each valuation, the cash you actually receive is 95% of certified value, and it arrives roughly 26 days (3.7 weeks) after the valuation date.
| Week | Cumulative spend (£k) | Cash in event | Cumulative cash received (£k) | Net position (£k) |
|---|---|---|---|---|
| 1–3 | 187.5 | None | 0 | -187.5 |
| 4 | 250.0 | Valuation 1 submitted (£250k) | 0 | -250.0 |
| 5–7 | 437.5 | Certificate 1 issued (week ~5) | 0 | -437.5 |
| 8 | 500.0 | Valuation 2 submitted (£250k). Payment 1 lands: £250k × 95% = £237.5k | 237.5 | -262.5 |
| 9–11 | 687.5 | Certificate 2 issued (week ~9) | 237.5 | -450.0 |
| 12 | 750.0 | Valuation 3 submitted (£250k). Payment 2 lands: £237.5k | 475.0 | -275.0 |
| 16 | 750.0 | Payment 3 lands: £237.5k | 712.5 | -37.5 |
After all three payments land, you are still £37.5k out of pocket. That is your 5% retention. Half (£18.75k) releases at Practical Completion. The other half stays locked until the DLP ends, typically 12 months later. Run six jobs like this at once and you have about £225k trapped in retention alone.
How to build this for any job in 10 minutes
Follow five steps. They work for any contract value and programme length.
- Plot your spend curve. Break the programme into weeks. Assign weekly spend based on your tender build-up. Front-loaded jobs (heavy M&E procurement in weeks 1–3, for example) will spike early. Back-loaded jobs (bespoke joinery arriving late) spike later. Don't assume even spend unless the job genuinely runs flat.
- Mark valuation dates. These are fixed by the contract. Under JCT, they're typically monthly from a defined start date. Plot each one on your timeline.
- Calculate the lag. From each valuation date, count forward: days to certificate, then days to final date for payment. Under JCT DB 2016, the gap from valuation to final payment date is typically 28 days. Add your real-world slippage. If your portfolio average is 35 days, use 35.
- Apply retention. Multiply each certified amount by 0.95 (for 5% retention) to get actual cash received. Then add the half-retention release at Practical Completion and the balance at DLP end as separate line items.
- Calculate net position per week. Subtract cumulative cash received from cumulative spend. The lowest point is your peak funding requirement. That is the number your finance director needs.
Adjusting for slippage and late certification
Late certification is the single biggest variable. If the Contract Administrator takes 10 days instead of 5 to issue the Interim Certificate, every payment shifts a week. On the £750k job above, that turns your week-8 net position from -£262.5k to -£325k because Payment 1 hasn't landed yet. The fix is simple maths: add the extra days to Step 3 and recalculate. Do this every month with real dates, not contract dates.
Programme slippage works differently. A two-week overrun doesn't just add two weeks of prelims (say £8k–£12k on a job this size). It also pushes your final valuation later, which pushes your final payment later. On a 12-week job that slips to 14 weeks, your peak funding requirement can jump by 20–25% because the spend curve extends but the payment curve extends further.
tightening to address the gap
Run fit-out delivery system
Setting: a £920,600 Cat B office fit-out in Birmingham under a JCT Design and Build sub-contract from a Main Contractor. The programme is 12 weeks and you are running two other live jobs. The risk is not "doing the work". It is starting workfaces with missing design, late materials, unaligned sub-contractor terms, no QA gates, and a chaotic final fortnight that burns your margin in snagging labour.
Weeks -2 to 0: mobilisation setup
- Set start conditions in money, not slogans. Prelims are £63,480 over 12 weeks, so £5,290 per week or £1,058 per working day. One false start in a meeting room with 3 operatives for 2 days at £218/day costs £1,308 in abortive labour before you touch rework or programme.
- Publish a mobilisation checklist with binary pass/fail gates. Before any trade sets foot on site, seven items must be green: (1) site access and welfare confirmed with Main Contractor, (2) H&S induction pack and RAMS (Risk Assessment and Method Statement) approved, (3) latest drawing set issued and logged in the drawing register, (4) all long-lead POs placed, (5) sub-contract orders signed with scope inclusions/exclusions, (6) valuation dates and payment terms confirmed, (7) site set-out survey complete with datum levels marked. If any gate is red, you don't mobilise that trade. A two-day delay at mobilisation costs £2,116 in prelims. A false start that triggers a week of re-sequencing costs £7,000+.
- Lock who signs what under JCT D&B, then force gaps into RFIs. Design responsibility sits with you for the Contractor's Designed Portion, and you pass portions down to sub-contractors where agreed. An RFI (Request for Information, a formal question to close a design gap) goes to the Main Contractor the day the gap is spotted, with a "needed by" date tied to the lookahead. Three RFIs in Week 1 (ceiling void depth clash, ironmongery schedule missing, feature wall finish not selected) cost £0 to raise and can save £2,000 to £4,000 each in rework.
Procurement: commit only what can delay you
On this job you sub-let M&E at £287,400, joinery at £143,650, and data/AV at £68,250. You also place early purchase orders for long-lead items, totalling £174,600 by end of Week 0. That is 19.0% of the contract value committed before your first Interim Certificate cash hits your bank. Order deadlines are "programme need date minus lead time minus 5 working days for approvals and admin". Miss the deadline and you pay prelims while trades stand.
| Long-lead item | Cost | Lead time | Order deadline | If missed, cost exposure |
|---|---|---|---|---|
| Bespoke joinery | £62,400 | 7 weeks | Week -1 (shop drawings approved) | 1 week slip = £5,290 prelims + £1,740 re-sequencing labour |
| Raised access floor | £41,800 | 4 weeks | Week 0 (layout frozen) | 3 days slip = £3,174 prelims + £1,580 abortive setting out |
| Specialist light fittings | £38,200 | 5 weeks | Week 0 (electrical layout frozen) | 1 week slip = £5,290 prelims + £1,220 weekend working |
| Ceiling grid + tiles | £32,200 | 2 weeks | Week 2 (services coordinated) | 2 days slip = £2,116 prelims + £980 wasted ceiling labour |
Sub-contractor control: onboarding and weekly grip
Onboard with one-page scope and payment facts. For the drylining package at £96,350, write inclusions and exclusions in plain words. One line like "firestopping to service penetrations by others" prevents a week-9 argument worth £7,240. Set valuation dates, payment 14 days after the Interim Certificate, and retention at 5%, so £4,818 held on that package until Practical Completion and the Defects Liability Period (the period after handover when the contractor fixes snags).
Run a Monday lookahead with a hard HOLD rule. The lookahead window is 3 to 6 weeks. Every line is either CONFIRMED or HOLD. "Confirmed" means latest drawing revision issued, materials delivered or delivery booked, and labour names and dates agreed. "Hold" means nobody starts that workface, even if the programme is shouting.
Track sub-contractor progress against programme weekly. Each Friday, the site manager records percentage complete per package against the baseline. A sub-contractor who is 10% behind programme at Week 4 gets a formal notice under the sub-contract and a recovery programme request. Wait until Week 8 to spot it and you're paying £4,200 in weekend overtime to recover two days, not the sub-contractor.
QA hold points and inspection gates
Most fit-out snag lists balloon because QA happens at the end, not during the work. Build hold points into the programme as hard gates. No following trade starts until the preceding trade passes its QA check.
| Hold point | Week | Who inspects | Pass criteria |
|---|---|---|---|
| First fix M&E before close-up | 3-4 | Site manager + M&E foreman | Services pressure tested, containment routes match coordinated drawing, fire collars fitted and photographed |
| Drylining before taping/jointing | 5 | Site manager | Board fixings at 150mm max centres, acoustic quilt fitted to spec, no gaps at head/floor tracks |
| Ceiling grid before tiles | 7 | Site manager + ceiling sub | Grid level within ±2mm over 3m, services above grid accessible and labelled, no missing hangers |
| Second fix complete before decorator | 9 | Site manager + QS walkthrough | All socket plates fitted, ironmongery installed, joinery scribed and filled, no exposed fixings |
Record each hold point on a standard site form: date, area, pass/fail, photos, signature. A 15-minute inspection at Week 5 that catches unfilled board joints saves 3 days of decorator rework at Week 10, worth roughly £1,860 in abortive labour plus a day of programme slip.
Weeks 10-12: snagging and close-out workflow
Start snagging at Week 10, not Week 12. Walk each completed zone room-by-room with a numbered snag list. Tag every item with trade, location, priority (A = blocks handover, B = cosmetic), and a 48-hour or 5-day fix deadline. On a job this size, expect 120 to 180 snags on the first pass if you've run the QA hold points above. Without hold points, that number doubles.
Issue snag lists to each sub-contractor by trade, not as one bulk document. The M&E sub-contractor gets their 35 items with photos and room references. The joinery sub gets their 22 items. Each sub-contractor signs off completed snags, and the site manager re-inspects before closing the item. In Archdesk, snag items raised on mobile site forms link back to the sub-contractor's package, so when you process their final valuation at Week 12, outstanding snags are visible against their retention balance of £4,818 (drylining) or £14,370 (M&E), giving you commercial grip without a separate spreadsheet.
At Week 11, compile the handover pack: O&M manuals, test certificates, as-built drawings, commissioning records, and the building warranty documentation. Chase these from sub-contractors at Week 9, not Week 12. Late O&M manuals are the single most common reason Practical Completion is delayed by the Main Contractor, and each day of delay costs you £1,058 in prelims you cannot recover.
The 12-week rhythm in one view
Takeaway
The non-obvious result is that margin protection on a 12-week fit-out is not one big decision. It is six small systems running together: mobilisation gates that stop false starts, procurement deadlines that prevent prelim burn, sub-contractor progress tracking that catches slippage at Week 4 not Week 9, QA hold points that cut your snag list in half, a snagging workflow that starts two weeks before handover, and a close-out process that chases O&M manuals before they delay Practical Completion. Run all six and you keep the £73,600 margin on this job. Drop two and you'll hand back £15,000 to £22,000 of it in abortive labour, overtime, and unrecovered prelims.
Fill the weekly dashboard
A weekly multi-project dashboard only works if it follows a fixed layout, fixed threshold rules, and a fixed calculation method. Below is the template, the step-by-step method for populating it, and a worked example across three live projects.
Dashboard template: one row per project, seven columns
Print this as a landscape A3 sheet or build it in a spreadsheet. Every row is one live project. Every column answers one question the board needs answered before Friday.
| Column | Field | What goes in it | Red threshold |
|---|---|---|---|
| 1 | Project ID | Job name, contract value, named PM | , |
| 2 | Programme | Days ahead / behind agreed programme baseline | 3+ days late = Red |
| 3 | Cost | Actual cost to date vs tendered cost to date (£ and %) | Over 3% of tendered cost to date = Red |
| 4 | Variations | Count of open variations, total £ value, oldest unquoted age in days | Any variation unquoted >14 days = Red |
| 5 | WIP | Work done but not yet certified (£ and % of contract value) | WIP >10% of contract value = Red |
| 6 | CVR forecast | Forecast final margin (£ and %) rebuilt from committed costs | Margin erosion >2 points from tender = Red |
| 7 | Cash action | One sentence: what is being done this week to fix each Red cell | No action against a Red cell = escalate to director |
Step-by-step: populating the dashboard each Wednesday
Wednesday gives you two days to act before the week closes. Here is the method, column by column.
Column 2, Programme. Pull the current programme from your last-planner or short-term programme. Compare the actual completion date of this week's planned activities against the baseline. Count the gap in working days. Example: Project A baseline says second-fix M&E in Zone 3 finishes Wednesday. It won't finish until Monday. That is 2 days late. Amber, not yet Red. Project B baseline says drylining in Level 2 finishes Monday. It finished the previous Thursday. That is 2 days ahead. Green.
Column 3, Cost. Sum all actual costs to date: labour timesheets, sub-contractor applications paid or accrued, material invoices, plant hire, and prelims spent. Compare against the tendered cost to date (not the full contract allowance, just the portion that should have been spent by this week per the tender programme). Calculate the variance as a percentage.
Column 4, Variations. Open your variation register. Count open items. Sum their estimated value. Flag the oldest unquoted item by age in days. If the QS hasn't issued a price within 14 days of receiving the instruction, that line turns Red.
Column 5, WIP. WIP = (cost of work done to date + margin earned to date) minus (total amount certified to date). This is money you've earned but the employer hasn't certified yet. Express it in £ and as a percentage of contract value.
Column 6, CVR forecast. Forecast final cost = cost to date + committed costs not yet invoiced + estimated cost to complete. Forecast final value = contract value + agreed variations + estimated value of pending variations (risk-weighted). Forecast final margin = forecast final value minus forecast final cost. Compare the margin percentage against the tender margin.
Worked example: three projects on one dashboard
| Project A Office fit-out, £1.4m |
Project B Retail unit, £680k |
Project C Lab refurb, £2.1m |
|
|---|---|---|---|
| Programme | 5 days late, Red | 2 days ahead, Green | 1 day late, Amber |
| Cost | Tendered to date £620k. Actual £649k. +£29k (+4.7%) Red | Tendered to date £310k. Actual £305k. −£5k (−1.6%) Green | Tendered to date £870k. Actual £896k. +£26k (+3.0%) Amber |
| Variations | 7 open, £48k est. Oldest unquoted: 22 days Red | 2 open, £9k est. Oldest unquoted: 6 days Green | 11 open, £134k est. Oldest unquoted: 31 days Red |
| WIP | £82k (5.9% of CV) Green | £74k (10.9% of CV) Red | £238k (11.3% of CV) Red |
| CVR margin | Tender 12.0%. Forecast 8.8%. Erosion 3.2pts Red | Tender 9.5%. Forecast 10.1%. +0.6pts Green | Tender 11.0%. Forecast 9.4%. Erosion 1.6pts Amber |
| Cash action | QS to issue variation quote pack (3 items, £22k) by Thursday. PM to add second ceiling gang to recover 3 of 5 lost days by next Friday. | PM to agree measured quantities with employer's QS before Monday valuation. Target: certify £74k WIP in Val 5. | QS to chase 4 variations >21 days, issue pricing by Friday. PM to raise interim application for £140k uncertified M&E work today. |
Project A shows why you read columns together, not in isolation. The programme slip (5 days) is driving the cost overrun (additional prelims and out-of-sequence working), and two unquoted variations mean £22k of recoverable cost sits unsubmitted. The cash action column ties both problems to a named person and a date this week.
Project B looks healthy on cost and programme, but £74k of WIP on a £680k job means the employer owes you almost 11% of the contract value. That's your cash funding their project. One action fixes it: agree the measure before the next valuation date.
Checklist: can you actually fill it?
Tick an item only if you can populate it every Wednesday from real inputs, not a Monday morning guess.
- Each live project has one row with contract value, current finish date, and a named PM who owns the numbers.
- Programme days are calculated from the current short-term programme, not from memory.
- Cost to date is built from timesheets, sub-contractor applications, material invoices, plant hire, and prelims, all pulled by Tuesday evening.
- Labour overspend is backed by hours and output (e.g. "240 hours for 110 lm of MF ceiling"), not just a cost total.
- The variation register is aged weekly. Each open item shows days since instruction, estimated value, and whether a quote has been issued.
- Every Red variation line names one owner, one action, and one date this week.
- WIP is calculated as (cost of work done + margin earned) minus total certified, not estimated from the last valuation.
- Each WIP Red line states the cause in plain English, e.g. "valuation backed off pending ceiling sign-off" or "variation not agreed so not claimed".
- CVR forecast margin is rebuilt weekly from committed costs, placed orders, and estimated cost to complete. If it's copied forward and tweaked, it's fiction.
- Every Red cell in the dashboard has a written cash action with an owner and a deadline before Friday.
Reading the result: 0–4 ticks: your dashboard will produce noise, not decisions. Fix inputs first: timesheets, POs, and a single variation register. 5–7 ticks: run it weekly for 4 weeks on your three biggest jobs and keep the thresholds strict. 8–10 ticks: roll it across every live site. One Red cell becomes one action, one owner, one deadline, every week. In Archdesk this maps directly to the CVR view and work in progress reporting: cost-to-date, committed cost, sub-contractor valuations, and certified value sit together per project, so the £74k WIP gap on Project B or the 3.2-point margin erosion on Project A surfaces the same week it opens, not at the quarterly review.
Stop variation cash bleed
Try this: You are running a 12-week Category B office fit-out under a typical JCT payment cycle. Base contract value is £900k. Retention is 5%. The Main Contractor has instructed £140k of variations. Only £60k is priced and agreed, and will be included in the next Interim Certificate. The remaining £80k is done or underway but still “to be sorted at final account”. Your next valuation is due in 5 days. Assume your direct cost of variation work is £0.80 for every £1.00 you recover (20% gross margin).
| Input | Figure |
|---|---|
| Base contract value | £900,000 |
| Retention | 5% |
| Variations instructed | £140,000 |
| Variations priced and agreed | £60,000 |
| Unagreed variation value | £80,000 |
| Direct cost ratio on variation work | 80% of recovered value |
| Delay to get the missing £80k certified | 2 months (two valuations later) |
Calculate two things. First, the working capital gap you fund for 2 months if you keep progressing the £80k without certification. Second, the gross margin you give away if the £80k gets pushed to final account and you only recover cost.
Pick three actions from the list in the worked solution. Your three picks must include one control, one evidence habit, and one hard conversation. Your answer should be a few lines of maths plus three bullets.
Show the worked solution
Step 1: Confirm what is actually at risk.
Instructed variations = £140,000.
Agreed and price-locked = £60,000.
Unagreed exposure = £140,000 − £60,000 = £80,000.
Step 2: Work out the cash gap you are funding for 2 months.
Direct cost ratio is 80%.
Cost you will pay out (labour, materials, sub-contractors) = 0.80 × £80,000 = £64,000.
If certification slips by 2 months, you are funding about £64,000 of working capital for 2 months.
Step 3: Add the retention drag so you don’t kid yourself about “being paid”.
Retention on the £80,000 (once it is agreed) = 5% × £80,000 = £4,000.
Board-pack wording in round numbers: “£64k WIP gap for two months, plus £4k trapped in retention.”
Step 4: Calculate the margin hit if it gets “sorted at final account” and you only recover cost.
Target sale value for that work = £80,000.
Target cost = £64,000.
Target gross margin = £80,000 − £64,000 = £16,000.
If you only recover cost at final account, recovery becomes £64,000.
Gross margin becomes £64,000 − £64,000 = £0.
Margin lost = £16,000 on one job. Run five live fit-outs and you can be giving away £80,000 of gross margin while also carrying £320,000 of funded cost.
Step 5: Choose three actions that recover position fastest.
- Control: Start a weekly variation log. One line per instruction. Fields: instruction ref, date instructed, scope, submitted value, agreed value, status, and ageing in days. Rule: any item older than 14 days gets escalated on Friday.
- Evidence habit: Get signed daywork sheets (time and materials tickets) daily for any instructed work done on daywork. One sheet per operative per day. Hours, task, location, and Main Contractor supervisor signature before they leave site. No signature means no daywork.
- Hard conversation: Run a 30-minute valuation pre-meet with the Main Contractor’s QS and force dates and consequences. Use this wording:
“We have £140k instructed. £60k is agreed. £80k is live and it won’t be valued unless we close it. I need three dates now for each item. The date you will return your assessment. The date we will agree the price. The date it will be included in the Interim Certificate. If we cannot agree by Friday, we proceed only on signed daywork sheets from Monday.”
Tracking variation status, pricing, and ageing in one place stops the Friday review turning into a hunt through emails, WhatsApps, and marked-up drawings.
What most people get wrong: they argue the last £500 of a rate while the real loss is ageing. Cash dies in the two-month gap, not in the final account meeting.
90-day scale plan
£15m turnover comes from controlled starts, hard delivery capacity rules, and cash protection that stops growth eating your margin. Below is a worked plan that turns the £15m target into specific start dates, headcount, cash buffers, and a repeatable weekly control routine you can adapt to your own mix of project sizes.
Worked 90-day plan: £15m fit-out contractor
This example assumes a firm currently running at £10m turnover, winning mostly commercial fit-out projects between £400k and £1.5m, with an average project duration of 16 weeks.
| Week | Action | Detail |
|---|---|---|
| 1–2 | Lock the starts plan | To move from £10m to £15m you need roughly £5m of additional live workload running concurrently. At an average project value of £750k and 16-week duration, that means 3 extra projects live at any time, requiring approximately 7 new project starts across the 90 days. Plot them: Start 1 (£800k) week 3, Start 2 (£650k) week 5, Start 3 (£900k) week 6, Start 4 (£700k) week 8, Start 5 (£750k) week 9, Start 6 (£600k) week 11, Start 7 (£850k) week 12. Total new secured work: £5.25m. Enter each start date into your tender tracker and don't move it without board sign-off. |
| 1–3 | Hire to capacity ratios | At £15m you will peak at roughly £6m–£7m live workload at any one time. Apply these ratios to calculate the gap:
Project Managers: 1 PM per £2.5m live = 3 PMs needed. If you have 2, recruit 1 PM by week 4, start date no later than week 6. Quantity Surveyors: 1 QS per 4 live projects. At peak you'll run 10–11 projects. You need 3 QSs. If you have 2, recruit 1 QS by week 3, start by week 5. Site Managers: 1 per live site. You likely need 2 additional site managers, staggered to match start dates: first by week 5, second by week 9. Admin/Coordinator: 1 per 100 supplier invoices/month. At £15m you'll process roughly 280–320 invoices a month. You need 3 coordinators. If you have 2, recruit 1 by week 6. |
| 2–4 | Size the cash buffer | Each £750k project costs roughly £55k–£70k per week in labour, materials, and subcontract payments during peak activity. From mobilisation to the first Interim Certificate clearing the bank typically takes 8–10 weeks on JCT fit-out. So each new start needs £440k–£700k of cash before a penny comes back. With 3 extra projects overlapping at peak, hold a minimum cash buffer of £1.3m to £1.5m. If your current cash reserves are below that, delay Start 6 and Start 7 until the first two valuations land. Write this gate into the starts plan: no mobilisation instruction unless the buffer is confirmed by the finance director that week. |
| 3–4 | Align payment cycles | For every new order, confirm valuation date (e.g. 25th of each month), due date (5 days after), final date for payment (14 days after due date under the Construction Act). Set subcontractor payment terms 7 days after you receive certified payment. This keeps your float positive on each project individually. Record these dates in a single payment calendar visible to the QS and finance team. |
| 4–6 | Standardise mobilisation | Issue a mobilisation pack for each start: signed contract/order, latest RIBA Stage 4 drawings, long-lead material orders placed, subcontract scopes issued, H&S pre-start file completed. No verbal go-aheads. The PM cannot open the site until the pack is signed off by the contracts manager. |
| 5 onwards | Weekly control meeting | Every Tuesday, 08:00–08:45. Same agenda, no exceptions. See schedule below. |
Weekly control meeting: fixed agenda
| Mins | Item | Owner | Output |
|---|---|---|---|
| 0–10 | Programme status: each PM flags red/amber/green and states days ahead or behind | PMs | Updated programme tracker |
| 10–20 | Labour burn: actual hours vs planned by trade, cost per operative day vs tender allowance | QS / PM | Over-burn actions |
| 20–30 | Procurement: outstanding POs, long-lead items at risk, committed cost vs budget | QS | PO chase list |
| 30–38 | Variation ageing: any variation unpriced for more than 5 working days gets escalated | QS | Priced variation issued or escalation owner named |
| 38–45 | WIP and cash: work done but not yet certified, cash buffer position vs threshold | Finance / QS | Start gate green/red for upcoming mobilisations |
Every red item gets one owner and one deadline before the meeting closes. No rolling reds for more than two consecutive weeks, or the contracts manager intervenes. In Archdesk, the CVR view feeds the WIP and cash section directly: cost-to-date, value earned, and forecast final account update as subcontractor valuations and PO commitments are entered, so a £180k WIP gap surfaces the same week it opens rather than at the end-of-quarter reconciliation.
What to learn next
- A one-page tender qualification sheet, because declining low-margin work protects capacity for the jobs that pay for the extra overhead you're about to add.
- A mobilisation pack template, because a bad start creates weeks of re-sequencing and extra prelims that never get recovered in the final account.
- Weekly CVR and WIP reporting, because growth multiplies small cost leaks and missed valuations into six-figure gaps before month-end reporting catches up.
Scaling a fit-out business works like scaling a delivery operation. More drops only help if dispatch, cash, and quality checks scale with them. Use this 90-day plan as a starting template. Adapt the project values and start weeks to your own pipeline, re-run the headcount ratios against your actual workload, confirm the cash buffer against your real payment cycles, and then lock the weekly meeting rhythm from day one. Repeat the cycle each quarter with tighter starts, cleaner valuations, and fewer surprises.
Frequently Asked Questions
How many live fit-out projects do I need to run at once to hit £15m turnover?
With an average contract value around £740k and a 12-week programme, you need roughly 1.7 new project starts per month and 5 to 6 live jobs running at any time. That means your delivery team, not your sales pipeline, sets the ceiling. If your contracts manager can only control 3 jobs properly, £15m will break your business before it grows it.
What tender win rate does a Cat B fit-out contractor need to support rapid growth?
A 25% win rate on a £740k average job means you need to price roughly 7 tenders per month to land 1.7 starts. If your win rate drops below 20%, your estimating team drowns in dead-end bids and your pipeline stalls. Track win rate weekly, not quarterly, so you spot the drop before it costs you a month of starts.
How do I stop variations bleeding cash on a 12-week JCT fit-out sub-contract?
On a £900k job with £140k of variations, only the £60k that is priced and agreed hits the next Interim Certificate. The other £80k sits unpaid until final account, which can be 6 months or more after handover. Price and issue variation accounts within 5 working days of instruction, with contemporaneous records attached, to keep agreed variation value above 70% of total variation value at all times.
What cash buffer does a fit-out company need before scaling from £5m to £15m?
Growth puts more cash on the conveyor belt between valuation and payment. With 5% retention, a 30-day payment cycle under JCT, and 2 or 3 new jobs mobilising at once, you can easily have £400k to £600k more tied up than your current working capital covers. Model your peak cash exposure month by month before you commit to new starts, not after.
What should a weekly multi-project dashboard track for a growing fit-out firm?
Use one row per project and seven columns: project name, programme status (days ahead or behind), cost to complete versus budget, variation value agreed versus instructed, next valuation date, cash collected versus certified, and top risk for the week. Print it on landscape A3 or build it in a spreadsheet. Review it at the same time every week with your contracts manager and QS, no exceptions.
What is the biggest delivery risk when scaling a fit-out contractor quickly?
The risk is not the physical work. It is starting on site with missing design information, late material deliveries, and sub-contractor terms that don't match your main contract obligations. A chaotic final fortnight on a 12-week programme burns your margin faster than any procurement saving recovers it. Set QA gates at weeks 2, 6, and 10 so problems surface early enough to fix cheaply.
How do I shorten the payment cycle on fit-out projects under JCT sub-contracts?
Know your three dates cold: valuation date, Interim Certificate date, and final date for payment. Submit your application on the valuation date, not a week late. Chase the Interim Certificate the day it is due. Most fit-out contractors lose 7 to 14 days per payment cycle through late submissions or missing backup documents, and that delay compounds across 5 or 6 live jobs into a serious cash gap.
What does a realistic 90-day plan look like for scaling a fit-out company to £15m?
Map specific start dates, not just revenue targets. Work backwards from £15m to monthly starts, then confirm you have the headcount, sub-contractor agreements, and cash buffer to support each start. A typical plan needs a contracts manager per 3 live jobs, a QS covering no more than £3m of live contract value, and enough working capital to cover 2 months of net outflow before valuations catch up.





