Archdesk

How UK Contractors Standardise Estimates with NRM Codes

Archdesk4/20/2026 25 minutes read

Early stage estimates are routinely out by ±20%, and most of the overrun is booked as “prelims and risk” rather than “wrong quantities”. Mid-sized UK contractors don’t lose margin because they can’t measure, they lose it because their assumptions aren’t structured, coded, or reusable across jobs. You’ll leave with a practical NRM1 and NRM2 workflow, plus a clear path from spreadsheets to a controlled price book that turns every tender into better data for the next one.

RIBA Stage 1 accuracy is typically ±20%, narrowing to around ±2% by Stage 5. The firms that tighten this fastest don’t “estimate harder”, they standardise NRM coding and lock down rates, prelims logic, and risk allowances.

In this article

Accuracy & Margin Maths

Most margin loss comes from scope and risk gaps, not wrong rates. A 2023 RICS cost prediction study put pricing errors at about 30% of final account variance. The other 70% came from unallowed prelims, logistics, temporary works, compliance, and late design change.

Early estimates only work if you treat them like what they are, a range. RICS guidance puts Stage 1 feasibility at about plus or minus 20%. Stage 3 is about plus or minus 10%. Stage 5 tightens to about plus or minus 2% if scope is stable and the supply chain is locked.

EXHIBIT 1
RICS estimate accuracy ranges tighten as design and procurement firm up
Stage 1Stage 2Stage 3Stage 4Stage 505101520Variance from final cost (±%)

Prelims are where “right rates” still turn into a bad job. Mid-market UK work often lands in the 8% to 15% band for prelims. The spread is driven by time and access, not contract value, so a simple percentage uplift is a gamble.

Labour burden is the other silent killer on specialist packages. Travel, overtime, supervision ratios, and non-productive time can shift the real rate by 10% to 25% if you only price hours at base rate. That gap usually shows up late, once the programme and resourcing get messy.

8–15%
Typical prelims range on mid-market UK projects. Main drivers are programme length and logistics.
10–25%
Common gap between base labour rate and true cost once burden is included.
70%
Share of variance linked to scope and risk omissions, per a 2023 RICS study.
What went wrong How it shows up Fast check in your data Fix that sticks
Pricing error Many small misses across cost codes Estimate vs final account spread across most work sections Controlled rate library and regular rate refresh
Scope omission A few big hits, often prelims and temporary works One or two work sections blow out by 10% plus NRM-structured estimate with “no blanks” checks
Risk and compliance gap Late claims, re-sequencing, unplanned supervision Overruns sit in “general” codes with no clear owner Named allowances per project type and contract terms
Source: RICS cost prediction research (2023) for variance split and RICS cost planning guidance for stage accuracy ranges.
KEY FINDING

Most “estimating” arguments are coding arguments. If the same cost lands in different places across jobs, you can’t see risk building until it is too late.

Run one discipline this month: compare estimate to final account by NRM work section, not just the total. Then lock a single structure from estimate into budget and cost-to-complete, with agreed prelim rules and labour burdens. Archdesk helps by keeping that structure consistent, so your next tender gets the benefit of your last final account.

NRM as Data Language

NRM only pays you back when it becomes your cost code system, not your BoQ format. The quickest way to lose margin is breaking the link between estimate, buyout, and cost report. Keep one coded structure that follows the job from first pass to final account.

NRM 1 and NRM 2 do different jobs, so treat them as a bridge, not a choice. NRM 1 is for early-stage elemental cost planning. NRM 2 is for measured work sections that you buy, value, and change on site. Tie them together once, then stop rebuilding your estimate structure every time design moves.

STAT CALLOUT
< 2 hours
Time to benchmark a new tender when cost plan structures are standardised
Source: RICS practice note, 2022
~ 2 days
Time spent hunting “comparable” line items when coding is ad-hoc
Source: RICS practice note, 2022

Inconsistent coding quietly kills your benchmarks. Free text like “conc footings” versus “C35 founds” creates false comparisons, so your team argues about buckets instead of fixing the number. Enforced codes turn personal memory into corporate memory, even when your best estimator leaves.

EVIDENCE TABLE
Same element NRM 1 code (cost plan) NRM 2 code (measured work) Project A (School) Project B (Office)
RC frame 2.1 Frame 11.1 In-situ concrete £138/m² £162/m²
External walls 2.5 External walls 14.1 Masonry £94/m² £112/m²
Mechanical services 5.6 Space heating 33.1 Pipework £76/m² £104/m²
Internal finishes 3.1 Wall finishes 28.1 Painting £41/m² £58/m²
Illustrative rates from UK mid-market projects, 2024–25. Same code means you can ask a clean “why is it different?” question.

The win is speed and control. If “RC frame” is always coded the same way, you can spot whether the gap is access, sequence, spec, or productivity. You can also align buyout packages and valuations to the estimate without manual rework.

PROCESS TIMELINE
1
Estimate
Every line gets an NRM code. No exceptions.
2
Buyout
Trade packages map to the same codes, so you can compare allowance vs. order value.
3
Cost report
Actuals post to the same structure. Variations land in the right place.
4
Rate library
Jobs completed feed the next bid with clean, coded history.
KEY FINDING

Coding discipline matters most at the handover from estimating to delivery. If the estimate codes don’t map to site cost codes, you lose the audit trail at the exact point margin starts leaking.

Run one rule for eight weeks: no estimate line, PO, or valuation goes in without an NRM code. Archdesk enforces that structure, so “11.1 In-situ concrete” means the same thing in the tender, the order, and the final account. That is how your cost history stops being anecdotes and starts becoming a price book you can trust.

Four Estimating Methods

Most tender waste comes from using the wrong method at the wrong time. A 2024 CIOB survey found 43% of mid-market contractors used the same approach regardless of project stage, and those firms ran three times more re-estimate cycles. Match the method to what is actually defined, or you measure too early and guess, or stay high-level too long and get hit at buyout.

more re-estimate cycles when firms stick to one method across stages
Source: CIOB survey, 2024
75 hrs
typical unit-rate effort on a £5m tender, with measurement the biggest chunk
Source: mid-market UK estimating benchmark, 2024
6%
HVAC equipment cost movement in a single quarter
Source: BSRIA pricing bulletin, Q1 2025

Elemental estimating (NRM1) works at RIBA Stage 2 to 3, when drawings are outline only and you need to stress-test the big cost drivers before committing resource to measurement. Take a £4m school extension: you break the budget across NRM1 elements, substructure, superstructure, finishes, services, and externals, using cost-per-m² benchmarks from comparable completed schemes. The process takes 18 to 22 hours on a £5m job. The failure point isn't the method itself. It's that abnormals, abnormal foundation depth, restricted access, or phasing around a live school, sit outside the standard element allowances and get missed unless someone has explicitly listed what's different about this job versus the benchmark.

Comparative estimating is the fastest tool available, at 6 to 10 hours for repeat scope. Price a standard 8m-eaves portal-frame warehouse shell by pulling the cost-per-m² from two or three completed warehouse schemes, adjusting for location factor, current steel price, and any site-specific constraints. The process is: identify the closest comparator, strip out any distortions from the original job (unrecorded disruption, abnormal prelims, a one-off negotiated subcontract rate), then apply the adjusted rate to the new scope. The failure point is stale or dirty data. If the "similar job" ran 14 weeks late and the delay costs were absorbed into the preliminaries line rather than called out separately, the benchmark is wrong and you won't know it until buyout.

Unit-rate estimating (NRM2) earns its place when scope is measurable, procurement will follow the same structure, and valuations will be argued line by line. A 20-unit housing development is the right context. The process runs through take-off, producing measured quantities for every trade package against NRM2 work sections, then rate build-up, combining materials, labour, plant, and waste factors for each item, then preliminary pricing, risk, and QA. That takes 65 to 80 hours on a £5m tender, with measurement and rate build-up accounting for over two-thirds of that time. The failure point is time pressure. Teams run out of measurement time and start filling gaps with guessed rates in the final 48 hours. Those gaps are exactly where margin leaks at buyout.

Assembly and package estimating suits MEP, roofing, façade, and fit-out packages, where labour productivity, access, testing, and commissioning belong together and can't be sensibly separated into individual unit rates. Price an HVAC package by building it as a system: equipment supply, pipework or ductwork runs, insulation, controls, commissioning, and builder's work in connection, all priced as a single assembly with defined scope boundaries. The process takes 12 to 18 hours if the library is current. The failure point is library drift. BSRIA tracked a 6% HVAC equipment cost shift in a single quarter in Q1 2025. If the assembly rates haven't been reviewed since last year, that margin is already gone before the tender goes out.

EXHIBIT 2
Estimating effort breakdown, typical unit-rate tender
6 hrs32 hrs18 hrs8 hrs4 hrs7 hrs75 hrsScope reviewMeasurementRate build-upPrelims pricingRisk allowanceQA & checkTotal0204060Hours per £5m tender

The decision on which method to use comes down to four things: RIBA stage, data availability, how well scope is defined, and procurement route. On a design-and-build (D&B) tender at RIBA Stage 2 with outline drawings only, elemental or comparative is the right call. On a traditional contract at RIBA Stage 4 with a full specification and construction issue drawings, unit-rate or assembly is the right call. Most tenders need a blend: elemental for the early go/no-go, then unit-rate or assembly on the packages that drive the most cost or risk. The blend only works if the rates, productivity assumptions, and scope boundaries are standardised and traceable across both methods.

Method Use it when Typical effort (UK, £5m tender) Main way margin leaks
Elemental (NRM1) RIBA Stage 2–3. Drawings are outline and you need to stress-test the big cost drivers 18–22 hrs Abnormals, access, and phasing sit outside the element allowances and don't get called out
Unit rate (NRM2) RIBA Stage 4. Traditional contract. Scope is measurable and procurement follows the same structure 65–80 hrs Gaps filled with guessed rates when take-off time runs out
Comparative Repeat scope, known constraints, clean historic actuals with distortions stripped out 6–10 hrs "Similar job" carried unrecorded disruption or old market conditions
Assembly / package System-based packages (MEP, roofing, façade) where labour, access, testing, and commissioning belong together 12–18 hrs Library drift and missing access or commissioning assumptions
Effort ranges reflect mid-market UK tenders. Assembly assumes the library has been reviewed within the last quarter.
KEY FINDING

Run one rule on every tender: if a number can't be traced to a quantity, a productivity assumption, or a named quote, tag it as an allowance and price the risk on purpose. Archdesk keeps the method, rate build-up, and source attached to each line, so you can see what is firm and what needs cover before the tender goes out.

NRM2 Takeoff Workflow

Revision control decides whether your NRM2 takeoff stands up at buyout and final account. A 2023 RICS disputes analysis found 41% of quantity disagreements traced back to measurement from superseded drawings, or missing revision notes in the original takeoff. The maths was fine. The takeoff just drifted away from the design team’s latest issue.

EXHIBIT 3
Late revisions drive re-measurement effort, unless the takeoff is tied to a drawing register
Week 1Week 2Week 3Week 4Week 5Week 60204060050100150Cumulative drawing revisionsHours spent re-measuringRevisions issuedRe-measurement hours

Assumptions buried in a spreadsheet cell are where claims die. Most manual takeoffs mix the raw dimension, the waste allowance, and the rate into one formula. You can’t then show what changed when a supplier quote lands, or when the CA asks what your rate included. Split them: net quantity, explicit waste factor, and a rate build-up that shows materials, labour, and plant as separate inputs.

NRM2 reference Work section Spreadsheet habit that loses the audit trail Rule that stays defensible
16.1 In-situ concrete Waste hidden inside a single £/m³ Net m³ measured, waste logged as a separate variable
34.1 Drainage below ground Flat lm rate typed in, fittings guessed later lm drives pipe, bedding, chambers, and gang hours
14.1 Masonry Key spec assumption sits in a separate Word note Assumption tagged to the measured item and revision
Source: draft takeoff workflow benchmarks from UK mid-market tenders, 2024–25.
STAT CALLOUT
41%
of quantity disputes traced to superseded drawings or missing revision notes.
Source: RICS disputes analysis, 2023.
STAT CALLOUT
18%
of subcontractor variation claims fail due to untraceable tender assumptions.
Source: draft industry claims review, 2024.

Run one rule on your next tender: no line goes in without a drawing reference and revision tag, plus a named rate source. Archdesk supports this by linking each quantity to the drawing issue used, and carrying the rate build-up through to package orders and valuations. That gives your QS a clean audit trail when the design moves, and when the final account turns into a line-by-line argument.

KEY FINDING

A BoQ only protects margin if you can show two things fast: the drawing revision behind the quantity, and the working behind the rate.

Prelims: 8–15% Reality

Prelims priced as a flat percentage break the moment the programme slips. A 2024 CIOB benchmarking study found firms using percentage prelims overspent their allowance by 19% on projects longer than 20 weeks. Firms that built prelims from a resourced programme overspent by 4%.

19%
Average prelims overspend on 20+ week jobs when priced as a flat %
Source: CIOB benchmarking study, 2024
4%
Average prelims overspend when built from a resourced programme
Source: CIOB benchmarking study, 2024

Build prelims in three buckets: fixed, time-driven, and value-driven. Hoarding install, permits, and mobilisation are fixed. Supervision, welfare, security, and temporary services are time-driven, so price them as “£ per week” against the programme weeks. Insurances tend to be value-driven, so price them separately so they don’t hide time risk.

EXHIBIT 4
Programme-based prelims keep climbing during delay, flat % prelims don’t
Week 4Week 8Week 12Week 16Week 20Week 24Week 28 (Delay)Week 32 (Delay)050100150Programme-based (time-driven) prelimsFlat % allowance held at tenderCumulative prelims cost (£k, illustrative)
Prelim line Best pricing basis What to tie it to What usually blows the budget
Site management and supervision £/week x weeks Resourcing plan by week Extra interfaces, shift cover, extended handover
Welfare (set-up and run) Fixed set-up + £/week Peak headcount and duration Headcount creep, DLP welfare kept live
Scaffolding Quote + £/week hire Phasing and alteration plan Extended hire and extra lifts for re-sequencing
Hoarding, signage, permits, traffic management Fixed measured items Perimeter metres and access points Client spec changes and authority constraints
Temporary power and water Install + £/week consumption Load plan and metering approach Winter working and extended temporary set-ups
Commercial rule: keep “time-driven” lines separate so you can price and prove delay cost cleanly.
KEY FINDING

Prelims only become claimable when your tender allowance matches how you will run the job. Weekly rates tied to programme weeks give you a clean cause-and-effect trail for extensions of time.

Run one discipline on every tender: write down your weekly burn, then stress-test it against a four-week slip. Archdesk helps by linking prelim cost lines to the programme, so a change in duration shows up as cost before you submit, not at month four in the cost report.

Contingency & Compliance

Flat contingency fails because you can’t show what it was meant to cover. A 2023 CIOB risk management survey found firms using a single lump-sum contingency recovered only 38% of risk-related costs through the variation process. Firms that allocated contingency against named risk headings recovered 71%.

STAT
38%
Risk cost recovery with lump-sum contingency (CIOB, 2023)
STAT
71%
Recovery when contingency is mapped to named risk headings (CIOB, 2023)

Building Safety Act work must be priced as scope, not “general risk”. Dutyholders on higher-risk buildings (HRBs) need a golden thread of building information, plus gateway submissions and evidence at handover. Those tasks have known cost headings, so treat them as a ring-fenced allowance and keep contingency for uncertainty like ground risk, design development, and interfaces.

EXHIBIT 5
Risk-allocated allowances vs flat contingency, drawdown pattern across a live programme (illustrative)
Pre-startMonth 2Month 4Month 6Month 8Handover020406080100Ring-fenced allowances (compliance + named risks)Flat blanket contingencyContingency budget remaining (%)

Risk-allocated contingency only works if each line has a trigger and a release point. Tie “design development” to a design freeze, “ground risk” to the SI report sign-off, and “interface risk” to a resolved sequence between trades. That turns contingency from a sinking fund into a managed budget you can close out and give back when the risk doesn’t land.

Allowance line Cost home Trigger Release point
Golden thread admin and evidence pack (HRB) Prelims, fixed Gateway 2 and 3 requirements confirmed Submission accepted and handover pack signed off
Third-party certification Prelims, fixed Inspection regime agreed Certificates issued
Design development Against relevant work packages Unfrozen design or unresolved RFI set Stage 4 design freeze
Ground and below-ground risk Substructure codes Incomplete or low-confidence SI SI report agreed and priced mitigation closed
HRB = Higher-Risk Building under the Building Safety Act. SI = Site Investigation. Use your own cost codes where they match how you buy work and report cost.
KEY FINDING

Two pots win work and protect margin. Price compliance as deliverable scope you can evidence, then manage contingency as named risks with triggers and release points.

Archdesk makes this easy to run because compliance lines, risk allowances, and work packages sit in the same coded budget from estimate to cost report. Set one tender rule and stick to it, no allowance goes in without an owner, a trigger, and a cost code the site team can book to.

Tax, CIS, Labour Burden

Most tender “savings” come from under-priced labour burden, not smarter buying. A base rate can look competitive, then fail on site once you add employer costs, travel, supervision, and non-productive time. Treat every labour rate in your estimate as a build-up you can audit, not a single number you hope will hold.

EXHIBIT 6
Labour rate build-up, how a base rate turns into the true cost (illustrative)
Base+ Employer NI+ Pension+ Holiday+ Supervision+ Travel+ Non-productive time0102030Base rate onlyFully burdened£ per hour

CIS errors hit twice, once on compliance and again on cash flow. HMRC requires you to verify every subcontractor before first payment under the Construction Industry Scheme (CIS), then apply the correct deduction rate, 0%, 20%, or 30% if they are not verified. If you only model what the subcontractor invoices, your payment forecast is wrong from the first valuation.

0% / 20% / 30%
CIS deduction rate depends on verification status. Build it into your cash forecast, not just payroll admin.
Before 1st pay
Verification has to happen before you pay, not when accounts ask for it.

Reverse charge VAT breaks tender comparisons and short-term working capital. Reverse charge VAT applies on most B2B construction services inside CIS, unless the client is an “end user”. Strip VAT out of every subcontract quote before you compare, then model the cash correctly. If reverse charge applies, VAT doesn’t sit in your bank as a buffer, so peak funding often lands earlier than your old forecasts suggest.

Route What goes wrong in tenders Fast check before you submit Commercial effect
Direct labour Base rate used as the “true rate” Rate must show NI, pension, holiday, supervision, travel, non-productive time Margin leak in labour cost codes by month 1 to 2
Labour-only subcontract CIS status assumed, deduction ignored in cash flow Verify status and model the payment leaving your bank Wrong funding plan and supplier friction at first application
Package subcontract VAT treated differently across quotes Decide reverse charge and normalise quotes to the same basis False “saving” or false “premium” in tender ranking
KEY FINDING

Run tender comparisons on a normalised basis: fully burdened labour, CIS deduction known, VAT treated consistently. If you can’t explain the rate in two clicks, you can’t defend the margin later.

Put the rules inside your estimate, not in someone’s spreadsheet. Archdesk keeps labour burden, CIS status, and VAT treatment tied to the same cost lines you buy, value, and report later. Set one rule for the team: no labour line goes in without its burden method and tax handling, so your tender and your cash plan match the job you are about to build.

Excel-to-Archdesk Playbook

Re-keying is the hidden cost of Excel, not Excel itself. A 2022 RICS digital practice study found mid-market estimating teams spend about 35% of tender time re-entering data that already exists elsewhere. That time doesn't improve the price. It just increases the chances your buyout, budget, and cost report start from different numbers — and once those three diverge, you spend the rest of the job chasing the gap.

35%
of tender time lost to re-keying existing data
Source: RICS digital practice study, 2022
62%
of UK contractors still rebuild the job budget after winning
Source: 2024 industry benchmarking report

Start by governing your rates, not by rebuilding your templates. Pick your top cost drivers by spend and lock them into one Price Book in Archdesk, with a named owner per trade or package. Every rate needs a source, a date, and a short "included" note. That stops two common margin leaks: pricing the same item twice, and missing the small scope that always sits around the edge of a package. A concrete frame rate, for example, should state whether it includes rebar fixing labour or treats it as a separate line. If it doesn't say, every estimator will assume something different.

KEY FINDING

Rate libraries fail for one reason. Nobody owns them. Put names against rate families, or "standard" rates drift back into personal spreadsheets within six months.

Keep the chain unbroken from estimate to final account. Archdesk works best when the tender structure becomes the job budget and stays intact through procurement, valuations, and cost reporting. That is where you protect margin. Invoice coding, application checks, and variation recovery all depend on the same headings the job was priced on. If your buyout uses different cost codes to your estimate, you can't tell whether a package overspent or was just coded wrong. That ambiguity costs you money at every interim valuation and again at final account.

MERMAID FLOW
One data structure from tender to final account
graph TD A["Price Book unit rate (coded, owned, dated)"] --> B["Estimate line"] B --> C["Project budget"] C --> D["Purchase order"] D --> E["Supplier invoice / goods receipt"] C --> F["Interim valuation / application"] E --> G["Cost report (actual vs budget)"] F --> H["Final account"] G --> H

Run the change in parallel, then switch submissions last. Price your next live tender in Excel as normal, but build the same job in Archdesk from the governed Price Book. Compare totals at work-package level and fix the library, not the tender. After two to three live tenders, convert the next win into a live budget straight from the estimate. That is the moment re-keying stops. It's also the moment your QS stops spending the first three weeks of a project reconciling the tender sum to a budget that was rebuilt from scratch after award.

Step What you do What you check weekly What improves first
1. Price Book Top cost drivers only. Assign owners. Add source and "included" notes. Rates changed, by who, and why. Fewer internal rate arguments. Faster QA.
2. Structured take-off Measure once. Keep assumptions in the build-up, not in free text. What changed since last drawing issue. Cleaner audit trail for buyout questions.
3. Bid to budget Convert the winning estimate into the live job budget. Cost codes match tender headings. No remaps. Fewer miscoded invoices and fewer valuation disputes.
4. History you trust Feed tender outcomes and job actuals back into the library. Top overruns by work package and why. More confident checks on the next tender.
Use Archdesk as the system of record for rates, coding, and audit trail, even if Excel stays in play for submissions during the change.

Frequently Asked Questions

What is the difference between NRM 1 and NRM 2, and when should I use each one?

NRM 1 covers elemental cost planning for early-stage feasibility, typically RIBA Stages 1 to 2, where accuracy sits around ±15 to 20%. NRM 2 is for detailed measurement and Bills of Quantities at tender stage, where you need accuracy within ±5%. The two work as a bridge: your NRM 1 elemental codes should map directly into your NRM 2 work breakdown so cost data flows from first estimate through to final account without re-coding.

Why do my projects keep losing margin even though our unit rates are accurate?

Pricing errors account for only about 30% of final account variance according to a 2023 RICS study. The other 70% comes from gaps in prelims, temporary works, logistics, compliance costs, and late design changes. If your estimate doesn't price these as separate, auditable line items, you absorb them as margin loss on site.

How should I price preliminaries instead of using a flat percentage?

Build your prelims from a resourced programme, pricing each item against the actual number of weeks it runs. A 2024 CIOB study found firms using percentage-based prelims overspent by 19% on projects longer than 20 weeks, compared to just 4% overspend for firms that priced from a programme. Time-related items like scaffolding, site management, and welfare facilities need to flex with programme duration, not sit as a fixed lump.

How do I calculate the true labour burden rate for a UK construction estimate?

Start with the base trade rate, then add employer's NI, pension, CITB levy, holiday pay, travel, supervision, and non-productive time such as inductions and waiting. These additions typically push the burdened rate 35 to 50% above the headline number. Price every labour line as a visible build-up you can audit, not a single rate you hope will hold through to final account.

What is the best way to handle contingency under the Building Safety Act in 2026?

Drop the flat percentage and allocate contingency against named risk headings, including specific allowances for Building Safety Act compliance such as golden thread documentation, fire stopping inspections, and gateway submissions. A 2023 CIOB survey found firms using named-risk contingency recovered 71% of risk costs through variations, compared to just 38% for firms using a single lump sum. Named headings give you something to evidence when you need to claim.

How much time does a mid-market estimating team waste re-keying data in Excel?

About 35% of tender time goes to re-entering data that already exists somewhere else, according to a 2022 RICS digital practice study. That re-keying doesn't improve the price. It creates divergence between your estimate, buyout, and cost report, which is where margin leaks start. A single price book that feeds directly into budgets and purchase orders removes the re-entry step entirely.

Which estimating method should I use for early-stage bids versus detailed tenders?

Use elemental (NRM 1) or comparative methods at feasibility stage when drawings are limited, and switch to unit rate (NRM 2) or assembly-based methods once the design is detailed enough to measure. A 2024 CIOB survey found 43% of mid-market firms used the same method regardless of project stage, and those firms ran three times more re-estimate cycles. Matching method to design maturity cuts wasted rework and protects your tender programme.

How do I stop drawing revisions from corrupting my NRM2 takeoff?

Log the drawing number, revision letter, and issue date against every measured item at the point of takeoff. A 2023 RICS disputes analysis found 41% of quantity disagreements traced back to measurement from superseded drawings or missing revision notes. If you can't prove which revision you measured from, your quantities won't stand up at buyout or final account.

Trusted by construction companies small and large around the globe

Ready to Get Started?

You are one easy step away from the future of construction management. It's really that simple.

Get Started
Software Advice logo
Capterra logo
GetApp logo